** [https://userweb.jlab.org/~aasatury/Fcal_LMS/fiber_prep/IMG_20230616_090218.jpg ~450 fibers were cut and half of them are already glued to donates]
 
** [https://userweb.jlab.org/~aasatury/Fcal_LMS/fiber_prep/IMG_20230616_090218.jpg ~450 fibers were cut and half of them are already glued to donates]
 
** [https://userweb.jlab.org/~aasatury/Fcal_LMS/fiber_prep/IMG_20230616_090332.jpg Glued fibers]
 
** [https://userweb.jlab.org/~aasatury/Fcal_LMS/fiber_prep/IMG_20230616_090332.jpg Glued fibers]
* '''Simulations/Analysis'''
 
 
=Agenda=
 
 
*'''Preparation of parts for ECAL modules''' -- Sasha
 
* '''Module fabrication'''  -- Sasha 
 
* '''Ongoing projects''' -- Sasha, all
 
* '''[[Testing of PMT dividers]]''' -- Sasha / Vlad
 
* '''[https://halldweb.jlab.org/wiki/index.php/FCAL_Insert_Module_Fabrication Procedures]'''
 
* '''Installation of the FCAL2 detector & integration to GlueX''' -- Sasha / Arshak
 
*'''Light monitoring system''' -- Arshak
 
 
* '''Simulations/Analysis'''
 
* '''Simulations/Analysis'''

Revision as of 22:42, 22 June 2023

Meeting time and location:


Agenda

  • Preparation of parts for ECAL modules -- Sasha
    • Crystals:
      - Received all crystals from CRYTUR [1].
      - Available for wrapping: 35 CRYTUR
    • Received 1000 long signal cables
    • Procurement parts for the LMS:
      - 16,400 ft of optical fibers delivered to the lab. 7,600 will be delivered in September.
      - Expect to receive all plastic caps for the LMS today (can start gluing them to fibers during next week)
      - Cutting Tedlar foils, wrapping PMT light guides, etc.
    • PO submitted for PMT dividers (expect to receive the first batch in the end of June)
  • Module fabrication -- Sasha
    • Fabricated modules: Total 1572 (remaining 24 + spares)
      - 10 modules fabricated during last week
    • Report from students
  • Ongoing projects -- Sasha, all
    • Visual inspections of fabricated modules [2]
      -1357 modules have been checked (572 SICCAS + 785 CRYTUR) [3]
    • Testing and labeling signal cables (connect flash ADC with the detector distribution panel) [4]
      - 725 long signal cables have been tested [5]
      - Cable tester and label maker
      - 12 bundles of signal cables are ready (out of 100)
    • Removing signal cables from the FCAL [6]
  • Testing of PMT dividers -- Sasha / Vlad
    • All dividers have been ordered (by Chris S.)
    • Preparing setups for testing modules and dividers
  • Proceedures
  • Installation of the FCAL2 detector & integration to GlueX -- Sasha / Arshak
  • Light monitoring system -- Arshak
  • Simulations/Analysis