* '''Ongoing projects''' -- Sasha, all
 
* '''Ongoing projects''' -- Sasha, all
 
** Visual inspections of fabricated modules [https://halldweb.jlab.org/detectors/fcal2/installation/meetings/19_05_2023/modules_qa.docx]   
 
** Visual inspections of fabricated modules [https://halldweb.jlab.org/detectors/fcal2/installation/meetings/19_05_2023/modules_qa.docx]   
**:  -1357 modules have been checked (572 SICCAS + 785 CRYTUR) [https://halldweb.jlab.org/detectors/fcal2/installation/meetings/19_05_2023/modules_shelves.jpg]
+
**:  -1586 modules have been checked  [https://halldweb.jlab.org/detectors/fcal2/installation/meetings/19_05_2023/modules_shelves.jpg]
 
** Testing and labeling signal cables (connect flash ADC with the detector distribution panel) [https://halldweb.jlab.org/wiki/index.php/Testing_and_labeling_cables]
 
** Testing and labeling signal cables (connect flash ADC with the detector distribution panel) [https://halldweb.jlab.org/wiki/index.php/Testing_and_labeling_cables]
 
**: - 725 long signal cables have been tested [https://halldweb.jlab.org/detectors/fcal2/installation/meetings/25_05_2023/boxes_with_labels.jpg]
 
**: - 725 long signal cables have been tested [https://halldweb.jlab.org/detectors/fcal2/installation/meetings/25_05_2023/boxes_with_labels.jpg]

Revision as of 22:57, 22 June 2023

Meeting time and location:


Agenda

  • Preparation of parts for ECAL modules -- Sasha
    • Crystals:
      - Received all crystals from CRYTUR [1].
      - Available for wrapping: 15 CRYTUR
      - Planned inspection of SICCAS crystals
    • Received 1100 long signal cables
    • Procurement parts for the LMS:
      - 16,400 ft of optical fibers delivered to the lab. 7,600 will be delivered in September.
      - Received all plastic caps
      - Cutting Tedlar foils, preparing silicon cookies, etc.
    • Will send all electronics components to the company to fabricate dividers on Monday next week
  • Module fabrication -- Sasha
  • Ongoing projects -- Sasha, all
    • Visual inspections of fabricated modules [2]
      -1586 modules have been checked [3]
    • Testing and labeling signal cables (connect flash ADC with the detector distribution panel) [4]
      - 725 long signal cables have been tested [5]
      - Cable tester and label maker
      - 12 bundles of signal cables are ready (out of 100)
    • Removing signal cables from the FCAL and rearranging signal cables in the hall [6]
  • Testing of PMT dividers -- Sasha / Vlad
    • All dividers have been ordered (by Chris S.)
    • Preparing setups for testing modules and dividers
  • Proceedures
  • Installation of the FCAL2 detector & integration to GlueX -- Sasha / Arshak
  • Light monitoring system -- Arshak
  • Simulations/Analysis