Difference between revisions of "JEF meeting, June 23, 2023"
From GlueXWiki
(→Agenda) |
(→Agenda) |
||
Line 16: | Line 16: | ||
**: - Received all plastic caps | **: - Received all plastic caps | ||
**: - Cutting Tedlar foils, preparing silicon cookies, etc. | **: - Cutting Tedlar foils, preparing silicon cookies, etc. | ||
− | |||
* '''Module fabrication''' -- Sasha | * '''Module fabrication''' -- Sasha | ||
<!-- ** [https://halldweb.jlab.org/detectors/fcal2/module_fabrication/status/fcal_fabrication.pdf Status of fabrication ] --> | <!-- ** [https://halldweb.jlab.org/detectors/fcal2/module_fabrication/status/fcal_fabrication.pdf Status of fabrication ] --> | ||
Line 31: | Line 30: | ||
** [https://docs.google.com/presentation/d/1euIA49SszoQmSM4Lxu1OtZ8OfjltgwzXIbXo6TPEB3s/edit#slide=id.p Report from students] | ** [https://docs.google.com/presentation/d/1euIA49SszoQmSM4Lxu1OtZ8OfjltgwzXIbXo6TPEB3s/edit#slide=id.p Report from students] | ||
* '''[[Testing of PMT dividers]]''' -- Sasha / Vlad | * '''[[Testing of PMT dividers]]''' -- Sasha / Vlad | ||
− | ** All dividers have been ordered ( | + | ** All dividers have been ordered; will send all electronics components to the company to fabricate dividers on Monday next week (Chris) |
** Preparing setups for testing modules and dividers | ** Preparing setups for testing modules and dividers | ||
* '''[https://halldweb.jlab.org/wiki/index.php/FCAL_Insert_Module_Fabrication Proceedures]''' | * '''[https://halldweb.jlab.org/wiki/index.php/FCAL_Insert_Module_Fabrication Proceedures]''' |
Revision as of 23:28, 22 June 2023
Meeting time and location:
- 9:30 am EST (JLab time) remote only
- Connection information
Agenda
- Preparation of parts for ECAL modules -- Sasha
- Crystals:
- - Received all crystals from CRYTUR [1].
- - Available for wrapping: 15 CRYTUR
- - Planned inspection of SICCAS crystals
- Received 1100 long signal cables
- Procurement parts for the LMS:
- - 16,400 ft of optical fibers delivered to the lab. 7,600 will be delivered in September.
- - Received all plastic caps
- - Cutting Tedlar foils, preparing silicon cookies, etc.
- Crystals:
- Module fabrication -- Sasha
- Fabricated modules: Total 1586 (remaining 24 + spares)
- Ongoing projects -- Sasha, all
- Visual inspections of fabricated modules [2]
- -1586 modules have been checked [3]
- Testing and labeling signal cables (connect flash ADC with the detector distribution panel) [4]
- - 725 long signal cables have been tested [5]
- - Cable tester and label maker
- - 12 bundles of signal cables are ready (out of 100)
- Removing signal cables from the FCAL and rearranging signal cables in the hall [6] [7]
- Cutting optical fibers (800 fibers have been cut), gluing plastic caps (380 recently glued)[8]
- Report from students
- Visual inspections of fabricated modules [2]
- Testing of PMT dividers -- Sasha / Vlad
- All dividers have been ordered; will send all electronics components to the company to fabricate dividers on Monday next week (Chris)
- Preparing setups for testing modules and dividers
- Proceedures
- Installation of the FCAL2 detector & integration to GlueX -- Sasha / Arshak / Vlad / Hakob
- Detector installation page
- Updates from the meetings with Tim's group [9]
- Discussion of the FCAL2 installation procedures [10]
- Final mapping of low-voltage cables
- Projects for summer students
- Summer Students (2023)
- Light monitoring system -- Arshak
- Simulations/Analysis