Difference between revisions of "JEF meeting, June 23, 2023"
From GlueXWiki
Line 10: | Line 10: | ||
**: - <span style="color:#FF0000"> Received all crystals from CRYTUR [https://halldweb.jlab.org/wiki/index.php/CRYTUR ]. </span> | **: - <span style="color:#FF0000"> Received all crystals from CRYTUR [https://halldweb.jlab.org/wiki/index.php/CRYTUR ]. </span> | ||
**: - Available for wrapping: 15 CRYTUR | **: - Available for wrapping: 15 CRYTUR | ||
− | **: - Expect to receive the last batch of crystals from SICCAS, plan to inspect (Jane) | + | **: - Expect to receive the last batch of crystals from SICCAS, plan to inspect in the middle of July (Jane) |
** Received 1100 long signal cables | ** Received 1100 long signal cables | ||
** Procurement parts for the LMS: | ** Procurement parts for the LMS: | ||
**: - 16,400 ft of optical fibers delivered to the lab. 7,600 will be delivered in September. | **: - 16,400 ft of optical fibers delivered to the lab. 7,600 will be delivered in September. | ||
**: - Received all plastic caps | **: - Received all plastic caps | ||
− | **: - Cutting Tedlar foils, preparing silicon cookies, etc. | + | **: - Cutting Tedlar foils, preparing silicon cookies [https://halldweb.jlab.org/detectors/fcal2/installation/meetings/06_23_2023/silicon_cookies.jpg], etc. |
* '''Module fabrication''' -- Sasha | * '''Module fabrication''' -- Sasha | ||
<!-- ** [https://halldweb.jlab.org/detectors/fcal2/module_fabrication/status/fcal_fabrication.pdf Status of fabrication ] --> | <!-- ** [https://halldweb.jlab.org/detectors/fcal2/module_fabrication/status/fcal_fabrication.pdf Status of fabrication ] --> |
Revision as of 09:23, 23 June 2023
Meeting time and location:
- 9:30 am EST (JLab time) remote only
- Connection information
Agenda
- Preparation of parts for ECAL modules -- Sasha
- Crystals:
- - Received all crystals from CRYTUR [1].
- - Available for wrapping: 15 CRYTUR
- - Expect to receive the last batch of crystals from SICCAS, plan to inspect in the middle of July (Jane)
- Received 1100 long signal cables
- Procurement parts for the LMS:
- - 16,400 ft of optical fibers delivered to the lab. 7,600 will be delivered in September.
- - Received all plastic caps
- - Cutting Tedlar foils, preparing silicon cookies [2], etc.
- Crystals:
- Module fabrication -- Sasha
- Fabricated modules: Total 1586 (need to fabricate 10 remaining spares)
- Ongoing projects -- Sasha, all
- Visual inspections of fabricated modules [3]
- -1586 modules have been checked [4]
- Testing and labeling signal cables (connect flash ADC with the detector distribution panel) [5]
- - 725 long signal cables have been tested [6]
- - Cable tester and label maker
- - 12 bundles of signal cables are ready (out of 100)
- Removing signal cables from the FCAL and rearranging signal cables in the hall [7] [8]
- - 400 signal cables removed, need to re-label and bundle
- - all cables have been re-arranged, two VXS crates can be removed (will be used by the ECAL)
- Cutting optical fibers (800 fibers have been cut), gluing plastic caps (380 recently glued)[9]
- Report from students
- Visual inspections of fabricated modules [3]
- Testing of PMT dividers -- Sasha / Vlad
- All dividers have been ordered; will send all electronics components to the company to fabricate dividers on Monday next week (Chris)
- Preparing setups for testing modules and dividers
- Proceedures
- Installation of the FCAL2 detector & integration to GlueX -- Sasha / Arshak / Vlad / Hakob
- Detector installation page
- Updates from the meetings with Tim's group [10]
- Discussion of the FCAL2 installation procedures [11]
- Final mapping of low-voltage cables
- Projects for summer students
- Summer Students (2023)
- Light monitoring system -- Arshak
- Simulations/Analysis