(Created page with "Meeting time and location: *9:30 am EST (JLab time) remote only * [https://halldweb.jlab.org/wiki-private/index.php/JEF_Weekly_Meeting#Connection_information Connection inform...")
 
Line 5: Line 5:
 
=Agenda=
 
=Agenda=
  
*'''Preparation of parts for ECAL modules''' -- Sasha  
+
'''Preparation of parts for ECAL modules''' -- Sasha  
 +
** Crystals:
 +
**: Received all crystals from CRYTUR [https://halldweb.jlab.org/wiki/index.php/CRYTUR ]. 
 +
**: Available for wrapping: 35 CRYTUR
 +
** Received 1000 long signal cables
 +
** Procurement parts for the LMS:
 +
**: 16,400 ft of optical fibers delivered to the lab. 7,600 will be delivered in September.
 +
**: Expect to receive all plastic caps for the LMS today (can start gluing them to fibers during next week)
 
* '''Module fabrication'''  -- Sasha   
 
* '''Module fabrication'''  -- Sasha   
 +
<!-- ** [https://halldweb.jlab.org/detectors/fcal2/module_fabrication/status/fcal_fabrication.pdf  Status of fabrication ] -->
 +
** Fabricated modules: <span style="color:#FF0000"> Total 1562 </span>
 +
**: 4 modules fabricated during last week  <!-- [[File:Fab_mod_may_2023.jpg]] -->
 +
** [https://docs.google.com/presentation/d/1euIA49SszoQmSM4Lxu1OtZ8OfjltgwzXIbXo6TPEB3s/edit#slide=id.p Report from students]
 
* '''Visual inspections of fabricated modules [https://halldweb.jlab.org/detectors/fcal2/installation/meetings/19_05_2023/modules_qa.docx] '''  
 
* '''Visual inspections of fabricated modules [https://halldweb.jlab.org/detectors/fcal2/installation/meetings/19_05_2023/modules_qa.docx] '''  
 +
*:  -1058 modules have been checked (273 SICCAS + 785 CRYTUR)  [https://halldweb.jlab.org/detectors/fcal2/installation/meetings/19_05_2023/modules_shelves.jpg]
 
* '''Testing and labeling cables'''
 
* '''Testing and labeling cables'''
 +
** [https://halldweb.jlab.org/wiki/index.php/Testing_labeling_cables Cable tester and label maker]
 +
**: - 600 long signal cables have been tested [https://halldweb.jlab.org/detectors/fcal2/installation/meetings/25_05_2023/boxes_with_labels.jpg]
 
* '''Removing signal cables from the FCAL''' [https://halldweb.jlab.org/wiki/index.php/Removing_FCAL_cables_from_the_detector]
 
* '''Removing signal cables from the FCAL''' [https://halldweb.jlab.org/wiki/index.php/Removing_FCAL_cables_from_the_detector]
 
* '''[[Testing of PMT dividers]]''' -- Sasha / Vlad
 
* '''[[Testing of PMT dividers]]''' -- Sasha / Vlad
 +
** Most parts for the active base have been arrived to the lab (including PCBs)
 +
** All dividers will be ordered during next week (by Chris S.)
 +
* '''[https://halldweb.jlab.org/wiki/index.php/FCAL_Insert_Module_Fabrication Proceedures]'''
 
* '''Installation of the FCAL2 detector & integration to GlueX''' -- Sasha / Arshak
 
* '''Installation of the FCAL2 detector & integration to GlueX''' -- Sasha / Arshak
 +
** [https://halldweb.jlab.org/wiki/index.php/FCAL_Installation Detector installation page]
 +
** Updates from the meetings with Tim's group [https://halldweb.jlab.org/wiki/index.php/FCAL_2_Design_Meetings]
 +
:: Discussion of the FCAL2 installation procedures [https://halldweb.jlab.org/wiki/index.php/FCAL_2_Installation_Meetings]
 +
** [https://halldweb.jlab.org/wiki/index.php/Distribution_of_signals_and_voltages Final mapping of low-voltage cables]
 +
** Manpower and division of tasks
 +
** [https://halldweb.jlab.org/wiki/index.php/List_of_tasks_and_manpower Projects for summer students]
 +
** [https://halldweb.jlab.org/detectors/fcal2/installation/students_2023/list_of_students_2023.xlsx Summer Students (2023) ]
 +
<!-- ** [https://halldweb.jlab.org/detectors/fcal2/installation/photos Disassembling FCAL] -->
 
*'''Light monitoring system''' -- Arshak
 
*'''Light monitoring system''' -- Arshak
 +
 
* '''Simulations/Analysis'''
 
* '''Simulations/Analysis'''
 
* [https://halldweb.jlab.org/doc-private/DocDB/ShowDocument?docid=6092 Talk at ECT* workshop next week] -- Simon
 
* [https://halldweb.jlab.org/doc-private/DocDB/ShowDocument?docid=6092 Talk at ECT* workshop next week] -- Simon

Revision as of 08:39, 9 June 2023

Meeting time and location:

Agenda

Preparation of parts for ECAL modules -- Sasha

    • Crystals:
      Received all crystals from CRYTUR [1].
      Available for wrapping: 35 CRYTUR
    • Received 1000 long signal cables
    • Procurement parts for the LMS:
      16,400 ft of optical fibers delivered to the lab. 7,600 will be delivered in September.
      Expect to receive all plastic caps for the LMS today (can start gluing them to fibers during next week)
  • Module fabrication -- Sasha
  • Visual inspections of fabricated modules [2]
    -1058 modules have been checked (273 SICCAS + 785 CRYTUR) [3]
  • Testing and labeling cables
  • Removing signal cables from the FCAL [5]
  • Testing of PMT dividers -- Sasha / Vlad
    • Most parts for the active base have been arrived to the lab (including PCBs)
    • All dividers will be ordered during next week (by Chris S.)
  • Proceedures
  • Installation of the FCAL2 detector & integration to GlueX -- Sasha / Arshak
Discussion of the FCAL2 installation procedures [7]