** Removing signal cables from the FCAL [https://halldweb.jlab.org/wiki/index.php/Removing_FCAL_cables_from_the_detector]
 
** Removing signal cables from the FCAL [https://halldweb.jlab.org/wiki/index.php/Removing_FCAL_cables_from_the_detector]
 
* '''[[Testing of PMT dividers]]''' -- Sasha / Vlad
 
* '''[[Testing of PMT dividers]]''' -- Sasha / Vlad
** Most parts for the active base have been arrived to the lab (including PCBs)
 
 
** All dividers have been ordered (by Chris S.)
 
** All dividers have been ordered (by Chris S.)
 +
** Preparing setups for testing modules and dividers
 
* '''[https://halldweb.jlab.org/wiki/index.php/FCAL_Insert_Module_Fabrication Proceedures]'''
 
* '''[https://halldweb.jlab.org/wiki/index.php/FCAL_Insert_Module_Fabrication Proceedures]'''
 
* '''Installation of the FCAL2 detector & integration to GlueX''' -- Sasha / Arshak
 
* '''Installation of the FCAL2 detector & integration to GlueX''' -- Sasha / Arshak

Revision as of 08:49, 9 June 2023

Meeting time and location:

Agenda

Preparation of parts for ECAL modules -- Sasha

    • Crystals:
      - Received all crystals from CRYTUR [1].
      - Available for wrapping: 35 CRYTUR
    • Received 1000 long signal cables
    • Procurement parts for the LMS:
      - 16,400 ft of optical fibers delivered to the lab. 7,600 will be delivered in September.
      - Expect to receive all plastic caps for the LMS today (can start gluing them to fibers during next week)
      - Cutting Tedlar foils, wrapping PMT light guides, etc.
    • - PO submitted for PMT dividers (expect to receive the first batch in the end of June)
  • Module fabrication -- Sasha
    • Fabricated modules: Total 1572 (remaining 24 + spares)
      10 modules fabricated during last week
    • Report from students
  • Ongoing projects -- Sasha, all
    • Visual inspections of fabricated modules [2]
      -1357 modules have been checked (572 SICCAS + 785 CRYTUR) [3]
    • Testing and labeling cables
      - Cable tester and label maker
      - 725 long signal cables have been tested [4]
    • Removing signal cables from the FCAL [5]
  • Testing of PMT dividers -- Sasha / Vlad
    • All dividers have been ordered (by Chris S.)
    • Preparing setups for testing modules and dividers
  • Proceedures
  • Installation of the FCAL2 detector & integration to GlueX -- Sasha / Arshak
Discussion of the FCAL2 installation procedures [7]