=Minutes=
 +
Attendees: Igal, Arshak, Bill, Jon, Phil, Susan, Igor, Liping, Sasha, Olga, Eugene, S.T.
 +
* 10 more crystals came from Crytur (55 remaining)
 +
* 15 crystals wrapped, 35 available for module fabrication
 +
* All ESR pre-shaped
 +
* Signal cables coming to lab
 +
* Ordered label maker for cables
 +
* Fibers for LMS coming to lab
 +
* Grand total fabricated modules = 1533
 +
** Students working on module inspection
 +
** Plan to check modules using LED and black box
 +
* Finalizing PMT divider design (modified op-amp and changed resistor chain)
 +
** Expect first batch of dividers soon (~4 weeks after order)
 +
* Discussed student participation at DNP meeting in Hawaii
 +
** Sasha will submit abstracts on behalf of students

Latest revision as of 08:06, 15 May 2023

Meeting time and location:

  • 9:30 am EST (JLab time) remote only
  • Zoom meeting ID: 161 050 9142 Passcode: 004965

Agenda

  • Preparation of parts for FCAL2 modules -- Sasha
    • Crystals:
      Received 40 crystals from CRYTUR [1]. Remaining 55 crystals will be sent to us during this and next month.
      Wrapped crystals: 15
      Available for wrapping: 10 SICCAS + 25 CRYTUR = 35
    • George (DSG group) finished with preshaping.
    • More than 400 long signal cables received, can start checking, bundling, labeling (receive labeling machine in a couple of weeks)
    • Procurement parts for the LMS
      Ordered 16,400 ft of optical fibers delivered to the lab. 7,600 will be delivered in September.
      Expect to receive fiber donats in a couple of weeks (will start working on the LMS)
  • Module fabrication -- Sasha
    • Fabricated modules: Total 1533
      46 modules fabricated during last week (Madison, Madylin, Hillary)
      Available for fabrication: 35
      42 modules fabricated using 'low quality' crystals for the stacking mockup and 'crunch' tests.
    • Report from students
  • Testing of PMT dividers -- Sasha / Vlad / Arshak
    • FCAL2 modules with dividers installed on the CCAL [2]
    • Met with Vlad P. on Tuesday. Fine tuned the divider circuit. Checking/tuning an amplifier; Chris S. ordered some OPS.
  • Installation of the FCAL2 detector & integration to GlueX -- Sasha / Arshak
Discussion of the FCAL2 installation procedures [4]

Minutes

Attendees: Igal, Arshak, Bill, Jon, Phil, Susan, Igor, Liping, Sasha, Olga, Eugene, S.T.

  • 10 more crystals came from Crytur (55 remaining)
  • 15 crystals wrapped, 35 available for module fabrication
  • All ESR pre-shaped
  • Signal cables coming to lab
  • Ordered label maker for cables
  • Fibers for LMS coming to lab
  • Grand total fabricated modules = 1533
    • Students working on module inspection
    • Plan to check modules using LED and black box
  • Finalizing PMT divider design (modified op-amp and changed resistor chain)
    • Expect first batch of dividers soon (~4 weeks after order)
  • Discussed student participation at DNP meeting in Hawaii
    • Sasha will submit abstracts on behalf of students