Line 16: Line 16:
 
* '''Installation of the FCAL2 detector & integration to GlueX''' -- Sasha / Vlad / Hakob
 
* '''Installation of the FCAL2 detector & integration to GlueX''' -- Sasha / Vlad / Hakob
 
**  Detector installation [https://logbooks.jlab.org/book/halld][https://halldweb.jlab.org/detectors/fcal2/installation/photos/install_fcal/students_detector1.jpg][https://halldweb.jlab.org/detectors/fcal2/installation/photos/install_fcal/students_detector.jpg]
 
**  Detector installation [https://logbooks.jlab.org/book/halld][https://halldweb.jlab.org/detectors/fcal2/installation/photos/install_fcal/students_detector1.jpg][https://halldweb.jlab.org/detectors/fcal2/installation/photos/install_fcal/students_detector.jpg]
 +
** Detector survey
 
** [https://halldweb.jlab.org/wiki/index.php/FCAL_Installation Detector installation page]
 
** [https://halldweb.jlab.org/wiki/index.php/FCAL_Installation Detector installation page]
 
** Updates from the meetings with Tim's group [https://halldweb.jlab.org/wiki/index.php/FCAL_2_Design_Meetings]
 
** Updates from the meetings with Tim's group [https://halldweb.jlab.org/wiki/index.php/FCAL_2_Design_Meetings]

Revision as of 22:23, 12 October 2023

Meeting time and location:

Agenda

  • Preparation of parts for ECAL -- Sasha
    • - signal cables: 1360 short cables, all long cables are ready
    • - signal patch panels are ready
    • - HV cables: 140 short cables (expect to receive most of them in 1-2 weeks), 36 long cables are in production
    • - HV distribution boards: have not yet been ordered (need to check multi-pin connector layout)
    • - LV cables: ordered, lead time unclear
    • - LV distribution boards: have not yet been ordered (need to finalize design, meeting with Chris and Stephanie on Monday next week)
    • - Optical fibers: received all
  • Testing of PMT dividers -- Sasha / Vlad
    • - Test setup is ready. About 30 dividers are ready for testing
  • Installation of the FCAL2 detector & integration to GlueX -- Sasha / Vlad / Hakob
  • Light monitoring system
  • Analysis/Simulation