Line 13: Line 13:
 
** - Optical fibers: received all
 
** - Optical fibers: received all
 
* '''Ongoing projects''' -- Sasha, all
 
* '''Ongoing projects''' -- Sasha, all
** Tested and labeled ~250 short signal cables [https://halldweb.jlab.org/detectors/fcal2/installation/meetings/10_13_2023/recently_labeled_cables.jpg Recently labeled cables in boxes)]
+
** Tested and labeled ~250 short signal cables ([https://halldweb.jlab.org/detectors/fcal2/installation/meetings/10_13_2023/recently_labeled_cables.jpg Recently labeled cables in boxes)]
 
** Final inspection of installed lead glass and lead tungstate modules [https://logbooks.jlab.org/entry/4196869]
 
** Final inspection of installed lead glass and lead tungstate modules [https://logbooks.jlab.org/entry/4196869]
 
** Meeting with the DSG group to discuss their involvement
 
** Meeting with the DSG group to discuss their involvement

Revision as of 20:17, 14 October 2023

Meeting time and location:

Agenda

  • Preparation of parts for ECAL -- Sasha
    • - signal cables: 1360 short cables, all long cables are ready
    • - signal patch panels are ready [1]
    • - HV cables: 140 short cables (expect to receive most of them in 1-2 weeks), 36 long cables are in production
    • - HV distribution boards: have not yet been ordered (need to check multi-pin connector layout)
    • - LV cables: ordered, lead time unclear
    • - LV distribution boards: have not yet been ordered (need to finalize design, meeting with Chris and Stephanie on Monday next week)
    • - Optical fibers: received all
  • Ongoing projects -- Sasha, all
  • Testing of PMT dividers -- Sasha / Vlad
    • - Test setup is ready. About 30 dividers are ready for testing
  • Installation of the FCAL2 detector & integration to GlueX -- Sasha / Vlad / Hakob
  • Light monitoring system
  • Analysis/Simulation