Difference between revisions of "JEF meeting, October 13, 2023"

From GlueXWiki
Jump to: navigation, search
Line 17: Line 17:
 
** Meeting with the DSG group to discuss their involvement
 
** Meeting with the DSG group to discuss their involvement
 
** [https://halldweb.jlab.org/detectors/fcal2/installation/students_2023/list_of_students_2023.xlsx Summer Students (2023) ]
 
** [https://halldweb.jlab.org/detectors/fcal2/installation/students_2023/list_of_students_2023.xlsx Summer Students (2023) ]
** All spare crystals (many of them are low quality) have been wrapped [https://halldweb.jlab.org/detectors/fcal2/installation/students_2023/spare_crystals.xlsx ]
+
** All spare crystals (many of them are low quality) have been wrapped [https://halldweb.jlab.org/detectors/fcal2/installation/meetings/10_13_2023/spare_crystals.jpg ]
 +
 
 
* '''[[Testing of PMT dividers]]''' -- Sasha / Vlad
 
* '''[[Testing of PMT dividers]]''' -- Sasha / Vlad
 
** - Test setup is ready. About 30 dividers are ready for testing
 
** - Test setup is ready. About 30 dividers are ready for testing

Revision as of 20:21, 14 October 2023

Meeting time and location:

Agenda

  • Preparation of parts for ECAL -- Sasha
    • - signal cables: 1360 short cables, all long cables are ready
    • - signal patch panels are ready [1]
    • - HV cables: 140 short cables (expect to receive most of them in 1-2 weeks), 36 long cables are in production
    • - HV distribution boards: have not yet been ordered (need to check multi-pin connector layout)
    • - LV cables: ordered, lead time unclear
    • - LV distribution boards: have not yet been ordered (need to finalize design, meeting with Chris and Stephanie on Monday next week)
    • - Optical fibers: received all
  • Ongoing projects -- Sasha, all