JEF meeting, October 13, 2023

From GlueXWiki
Revision as of 22:39, 12 October 2023 by Somov (Talk | contribs) (Agenda)

Jump to: navigation, search

Meeting time and location:

Agenda

  • Preparation of parts for ECAL -- Sasha
    • - signal cables: 1360 short cables, all long cables are ready
    • - signal patch panels are ready
    • - HV cables: 140 short cables (expect to receive most of them in 1-2 weeks), 36 long cables are in production
    • - HV distribution boards: have not yet been ordered (need to check multi-pin connector layout)
    • - LV cables: ordered, lead time unclear
    • - LV distribution boards: have not yet been ordered (need to finalize design, meeting with Chris and Stephanie on Monday next week)
    • - Optical fibers: received all
  • Ongoing projects -- Sasha, all
    • Tested and labeled ~250 short signal cables
    • Visual inspection of installed lead glass and lead tungstate modules
    • Summer Students (2023)
  • Testing of PMT dividers -- Sasha / Vlad
    • - Test setup is ready. About 30 dividers are ready for testing
  • Installation of the FCAL2 detector & integration to GlueX -- Sasha / Vlad / Hakob
  • Light monitoring system
  • Analysis/Simulation