=Minutes=
 +
Attendees:  Liping,Igal,Jared,Tim W.,Zisis,Phil,Tim B.,Jane,Sasha,Josh,Azizah,S.T.
 +
* Jane visited Shanghai company and inspected 70 out of 175 new crystals as of her report on Friday
 +
** Transmission looked okay, except the company reported values at 650 nA instead of 620 nA
 +
*** Want to ask company to give measurements consistent with previous ones
 +
*** Need to do cross calibration of transmittance measurements
 +
** Some crystals had chips, some issues with quality control with chamfers, but generally better than previous batch
 +
** Found 3 discolored crystals:  1 yellow, 1 brown, 1 purple -- Sasha pointed out that the discoloration is our major concern
 +
*** Don't have company send us these?
 +
* 50 more steel shields have been delivered, need to be annealed.
 +
* Waiting for light guide company to demonstrate polishing improvement, then order 150
 +
* Sasha installed last batch of crystals in PS setup before the run ended
 +
** No big surprises (light output generally okay, except for 2 outliers)
 +
** Want to do transmittance measurements for 2 bad ones, need access to Carl Zorn's lab, no word yet
 +
** Plan to modify setup to make it easier to swap out a set of 12 crystals
 +
* Sasha installed 3 modified dividers in COMCAL, but 2 needed to be modified at the last minute and did not work
 +
** Will do more tests on the bench
 +
* Enough hardware is available to build 20 more modules
 +
** Need to finalize brazing procedure
 +
** Work on inventory and coming up with a plan to proceed the week of 9/28/20
 +
* Work is proceeding on JEF picture archive

Latest revision as of 07:58, 28 September 2020

Meeting time and location= 9:00 am EST (JLab time) Bluejeans only


Connection instructions

We are using BlueJeans Video/Audio conferencing. Our meeting ID number is 992533564. Click "Expand" for more details.

  • Make sure you have created a BlueJeans account via your JLab CUE account using this link:
  • If connecting via Web Browser: click this link (no passcode is needed):
  • If connecting via Phone: Dial one of the following numbers and then enter the meeting ID above and hit "#" or "##"
  • If connecting via Polycom unit:
    • Dial 199.48.152.152 or bjn.vc
    • Enter meeting ID above

Agenda

  • SICCAS crystals
-PWO test results

Minutes

Attendees: Liping,Igal,Jared,Tim W.,Zisis,Phil,Tim B.,Jane,Sasha,Josh,Azizah,S.T.

  • Jane visited Shanghai company and inspected 70 out of 175 new crystals as of her report on Friday
    • Transmission looked okay, except the company reported values at 650 nA instead of 620 nA
      • Want to ask company to give measurements consistent with previous ones
      • Need to do cross calibration of transmittance measurements
    • Some crystals had chips, some issues with quality control with chamfers, but generally better than previous batch
    • Found 3 discolored crystals: 1 yellow, 1 brown, 1 purple -- Sasha pointed out that the discoloration is our major concern
      • Don't have company send us these?
  • 50 more steel shields have been delivered, need to be annealed.
  • Waiting for light guide company to demonstrate polishing improvement, then order 150
  • Sasha installed last batch of crystals in PS setup before the run ended
    • No big surprises (light output generally okay, except for 2 outliers)
    • Want to do transmittance measurements for 2 bad ones, need access to Carl Zorn's lab, no word yet
    • Plan to modify setup to make it easier to swap out a set of 12 crystals
  • Sasha installed 3 modified dividers in COMCAL, but 2 needed to be modified at the last minute and did not work
    • Will do more tests on the bench
  • Enough hardware is available to build 20 more modules
    • Need to finalize brazing procedure
    • Work on inventory and coming up with a plan to proceed the week of 9/28/20
  • Work is proceeding on JEF picture archive