Difference between revisions of "JEF meeting, September 29, 2023"

From GlueXWiki
Jump to: navigation, search
Line 9: Line 9:
 
**: - Plan to send back about 10 crystals  
 
**: - Plan to send back about 10 crystals  
 
** Received 1100 short signal cables [https://halldweb.jlab.org/detectors/fcal2/installation/photos/label_signal/short_signal.jpg]  
 
** Received 1100 short signal cables [https://halldweb.jlab.org/detectors/fcal2/installation/photos/label_signal/short_signal.jpg]  
** Procurement parts for the LMS:
+
** Received 24,400 ft of optical fibers.  
**: - Waiting for 7,600 ft of optical fibers. PR department prepared PO but forgot to send it out
+
 
* '''Module fabrication'''  -- Sasha   
 
* '''Module fabrication'''  -- Sasha   
 
<!-- ** [https://halldweb.jlab.org/detectors/fcal2/module_fabrication/status/fcal_fabrication.pdf  Status of fabrication ] -->
 
<!-- ** [https://halldweb.jlab.org/detectors/fcal2/module_fabrication/status/fcal_fabrication.pdf  Status of fabrication ] -->

Revision as of 09:18, 29 September 2023

Meeting time and location:

Agenda

  • Preparation of parts for ECAL modules -- Sasha
    • Crystals:
      - Received 70 crystals from SICCAS. Visual inspection: 4 dim crystals, 8 with many chips (consider to send them back to SICCAS) [1][2]
      - Plan to send back about 10 crystals
    • Received 1100 short signal cables [3]
    • Received 24,400 ft of optical fibers.
  • Module fabrication -- Sasha
    • All modules have been fabricated, checked, and inventorized (about 1610 modules in total)
  • Ongoing projects -- Sasha, all
    • Visual inspections of fabricated modules [4] - done
    • All crystals moved to Hall D[5] [6][7] - done
    • Tested, labeled, and bundled all 100 (+ 2 spares) [8] signal cables connected from the flash ADC to the patch panel [9] - done
    • Test and label 1100 short signal cables - ongoing
    • Tested fabricated modules using LMS [10] - done (need to update the wiki page)
    • Cutting optical fibers and gluing plastic caps [11], waiting for 7600 ft of optical fibers
    • Report from students
    • Refurbished (remove soldering bumps and rewrap) 42 modules. One more layer of the detector will be installed today.
    • Need to wrap and fabricate about 30 modules using newly received crystals (will replace some already existing modules with low-quality crystals). Plan to finish with this during next week.
    • Preparing optical fibers for the LMS
  • Testing of PMT dividers -- Sasha / Vlad
    • -Tested 6 dividers from the first batch. Asked to produce all remaining dividers. Expect to receive some of them in a couple of weeks
  • Proceedures
  • Installation of the FCAL2 detector & integration to GlueX -- Sasha / Arshak / Vlad / Hakob
  • Light monitoring system -- Arshak
  • Analysis/Simulation