Difference between revisions of "Jul 24, 2012 Readout"

From GlueXWiki
Jump to: navigation, search
(Tentative Agenda)
Line 29: Line 29:
 
# Announcements
 
# Announcements
 
# Review of Action Items
 
# Review of Action Items
# Update from Athens: monitoring
+
## E-mail update from Christina (edits by Elton)
#* [[BCAL_Monitoring#Photos_and_Plots | Photos of initial version of support]]
+
## Update from Athens: monitoring
 +
##* I was in Geneva last week and clarified the Farnell order and everything, which  will be delivered tomorrow.
 +
##* The pacing items are the DigiKey connectors-the ones which connect the flex cable from the LED to the control board : one goes on the LED boards and four on the control boards. These are the ones which will be delivered around 20th August (the last items before stuffing).
 +
##* The LED's were delivered and I carried back in Athens, as well as the 4,000 mini boards.
 +
##* The flex cables have delivery date around 6th of August.
 +
##* I will also start the orders for the control boards,
 +
##* Personnel is disappearing  for August vacations, but will try to identify personnel for testing.
 +
## [[BCAL_Monitoring#Photos_and_Plots | Photos of initial version of support]]
 +
##* First support strip to glue LED boards after light guides are installed did not work because it could not reach sufficiently deep between the smallest light guides.  Elton and Tim are revising the support to address the issues that were found.
 
# Update from USM
 
# Update from USM
 
## [[Media:USMReport23.pdf|SiPM Update]] (Javiera)
 
## [[Media:USMReport23.pdf|SiPM Update]] (Javiera)

Revision as of 14:51, 24 July 2012

Teleconference Time: 11:00 a.m. EST

  • ESNET (Number is 8542553) and EVO session (GlueX Calorimetry meeting room)
  • Phone connection only upon request.
    • +1-866-740-1260 : US and Canada
    • +1-303-248-0285 : International
    • then use participant code: 3421244# (the # is needed when using the phone)
    • OR from www.readytalk.com type access code 3421244 into "join a meeting" without the # (you need java plugin)

Participant Direct Lines

  • JLab Phone: in CC F326 is 757-269-6337 (usual room)
  • JLab Phone in CC L207 is 757-269-7084
  • Phone in the Regina Videoconference Suite is 306-585-4204
  • Athens Phone: in Christina's office is 011-30-210-727-6947

Items for followup from previous meeting

  1. SiPMs
    • Investigate the optimum overbias setting for the SiPMs (Serguei and Orlando)
    • Understand how Orlando's data relates to the SiPM specifications (Elton et al)
  2. Light guides
    • Send list of light guides that are out of tolerance (Iñaki)

Presentations from recent meetings

Tentative Agenda

  1. Announcements
  2. Review of Action Items
    1. E-mail update from Christina (edits by Elton)
    2. Update from Athens: monitoring
      • I was in Geneva last week and clarified the Farnell order and everything, which will be delivered tomorrow.
      • The pacing items are the DigiKey connectors-the ones which connect the flex cable from the LED to the control board : one goes on the LED boards and four on the control boards. These are the ones which will be delivered around 20th August (the last items before stuffing).
      • The LED's were delivered and I carried back in Athens, as well as the 4,000 mini boards.
      • The flex cables have delivery date around 6th of August.
      • I will also start the orders for the control boards,
      • Personnel is disappearing for August vacations, but will try to identify personnel for testing.
    3. Photos of initial version of support
      • First support strip to glue LED boards after light guides are installed did not work because it could not reach sufficiently deep between the smallest light guides. Elton and Tim are revising the support to address the issues that were found.
  3. Update from USM
    1. SiPM Update (Javiera)
    2. Light guides (Iñaki)
  4. Status of testing at JLab
    1. Hall-D ELOG.
    2. Update on the analysis of the production units (Ben St. Laurent)
    3. Optimal bias voltage (Yi Qiang)
  5. BCAL Beam Tests 2012:
  6. Status of work at Regina
    1. BCAL hdgeant (David L.)
    2. BCAL Cosmics at Regina
  7. Other

Minutes

Attending: