(Created page with "= Meeting Time and Place == Thursday July 09, 2020, 1:30pm Bluejeans https://bluejeans.com/735541157/3638?src=calendarLink * Present - Elton, Dave, Bobby, Ilya, Rory (remote)...") |
(→Agenda) |
||
Line 6: | Line 6: | ||
== Agenda == | == Agenda == | ||
− | * Minutes from last meeting https://halldweb.jlab.org/wiki/index.php/ | + | * Minutes from last meeting https://halldweb.jlab.org/wiki/index.php/June_18,_2020_CPP_Design_Meeting |
* FY2020 Procurement Priorities [[Media:CPP_Procurement_Priorities.pdf]] | * FY2020 Procurement Priorities [[Media:CPP_Procurement_Priorities.pdf]] | ||
* Design/Fab/Install schedule [[Media:CPP_install_schedule_2021.pdf]] | * Design/Fab/Install schedule [[Media:CPP_install_schedule_2021.pdf]] |
Revision as of 08:15, 10 July 2020
Meeting Time and Place =
Thursday July 09, 2020, 1:30pm Bluejeans https://bluejeans.com/735541157/3638?src=calendarLink
- Present - Elton, Dave, Bobby, Ilya, Rory (remote)
Agenda
- Minutes from last meeting https://halldweb.jlab.org/wiki/index.php/June_18,_2020_CPP_Design_Meeting
- FY2020 Procurement Priorities Media:CPP_Procurement_Priorities.pdf
- Design/Fab/Install schedule Media:CPP_install_schedule_2021.pdf
- Shielding Simulation - Ilya
- 3D model - show progress
- Upcoming run, possible tests Media:CPP_Tests.pdf
Assume that nominal the GlueX configuration consists of
- No Pb shielding
- DIRC installed
- Solenoid field at 1350 A
CPP Test Configuration
- With and without Pb shielding
- DIRC removed
- Solenoid field at 1350 A (no change)
- CPP test DAQ setup: 2 hrs
- Repeat measurement with nominal GlueX configuration: 2 hrs
- Configure experiment for CPP Test: 38 hours
- Start with no DIRC, no shielding
- Take data: 2 hours
- Install Pb shielding: 6 hours
- Take data: 2 hours
- Restore nominal GlueX configuration: 26 hours.
Total time = 2 + 2 + 38 + 2 + 6 + 2 + 26 = 76 hours ~ 3 days
- Things to work out
- Gas line manifold
- Adjustable lead absorber
- Alignment hardware
- Complete structural analysis
- Develop Detailed installation plan
- Develop Design/operational/Maintenance Requirements
Minutes and Action Items
- Reviewed minutes of last meeting
- Set up new meeting in 2 weeks