* Present - Elton, Dave, Bobby, Ilya, Rory (remote)
+
* Present - Elton, Dave, Bobby, Ilya, Eugene, Rory (remote)
  
 
== Agenda ==
 
== Agenda ==
 
* Minutes from last meeting https://halldweb.jlab.org/wiki/index.php/June_18,_2020_CPP_Design_Meeting
 
* Minutes from last meeting https://halldweb.jlab.org/wiki/index.php/June_18,_2020_CPP_Design_Meeting
* FY2020 Procurement Priorities [[Media:CPP_Procurement_Priorities.pdf]]
+
* Upcoming run, possible testschedule [[Media:CPP_Tests_Aug2020.pdf]]
* Design/Fab/Install schedule [[Media:CPP_install_schedule_2021.pdf]]
+
* Shielding Simulation - Ilya
+
* 3D model - show progress
+
* Upcoming run, possible tests [[Media:CPP_Tests.pdf]]
+
 
Assume that nominal the GlueX configuration consists of
 
Assume that nominal the GlueX configuration consists of
 
* No Pb shielding
 
* No Pb shielding
Line 21: Line 17:
 
* DIRC removed
 
* DIRC removed
 
* Solenoid field at 1350 A (no change)
 
* Solenoid field at 1350 A (no change)
 
 
** CPP test DAQ setup: 2 hrs
 
** CPP test DAQ setup: 2 hrs
 
** Repeat measurement with nominal GlueX configuration: 2 hrs
 
** Repeat measurement with nominal GlueX configuration: 2 hrs
** Configure experiment for CPP Test: 38 hours
+
** Configure experiment for CPP Test: 12 hours
 
** Start with no DIRC, no shielding
 
** Start with no DIRC, no shielding
 
** Take data: 2 hours
 
** Take data: 2 hours
** Install Pb shielding: 6 hours
+
** Install Pb shielding: 2 hours
 +
** Take data: 2 hours
 +
** Install 2 Pb shields: 2 hours
 
** Take data: 2 hours
 
** Take data: 2 hours
** Restore nominal GlueX configuration: 26 hours.
+
** Restore nominal GlueX configuration: 4 hours.
  
Total time = 2 + 2 + 38 + 2 + 6 + 2 + 26 = 76 hours ~ 3 days
+
Total time = 30 hours
  
 
* Things to work out
 
* Things to work out

Revision as of 08:19, 10 July 2020

Meeting Time and Place =

Thursday July 09, 2020, 1:30pm Bluejeans https://bluejeans.com/735541157/3638?src=calendarLink

  • Present - Elton, Dave, Bobby, Ilya, Eugene, Rory (remote)

Agenda

Assume that nominal the GlueX configuration consists of

  • No Pb shielding
  • DIRC installed
  • Solenoid field at 1350 A

CPP Test Configuration

  • With and without Pb shielding
  • DIRC removed
  • Solenoid field at 1350 A (no change)
    • CPP test DAQ setup: 2 hrs
    • Repeat measurement with nominal GlueX configuration: 2 hrs
    • Configure experiment for CPP Test: 12 hours
    • Start with no DIRC, no shielding
    • Take data: 2 hours
    • Install Pb shielding: 2 hours
    • Take data: 2 hours
    • Install 2 Pb shields: 2 hours
    • Take data: 2 hours
    • Restore nominal GlueX configuration: 4 hours.

Total time = 30 hours

  • Things to work out
    • Gas line manifold
    • Adjustable lead absorber
    • Alignment hardware
    • Complete structural analysis
    • Develop Detailed installation plan
    • Develop Design/operational/Maintenance Requirements

Minutes and Action Items

  • Reviewed minutes of last meeting
  • Set up new meeting in 2 weeks