== Minutes and Action Items ==
 
== Minutes and Action Items ==
 
* Reviewed minutes of last meeting
 
* Reviewed minutes of last meeting
 +
* Bobby presented the configuration and the process was discussed - generally ok
 +
* Need to add platform to set lead on so 1 person can change it
 
* Set up new meeting in 2 weeks
 
* Set up new meeting in 2 weeks

Revision as of 09:29, 10 July 2020

Meeting Time and Place =

Thursday July 09, 2020, 1:30pm Bluejeans https://bluejeans.com/735541157/3638?src=calendarLink

  • Present - Elton, Dave, Bobby, Ilya, Eugene, Rory (remote)

Agenda

Assume that nominal the GlueX configuration consists of

  • No Pb shielding
  • DIRC installed
  • Solenoid field at 1350 A

CPP Test Configuration

  • With and without Pb shielding
  • DIRC removed
  • Solenoid field at 1350 A (no change)
    • CPP test DAQ setup: 2 hrs
    • Repeat measurement with nominal GlueX configuration: 2 hrs
    • Configure experiment for CPP Test: 12 hours max
    • Start with no DIRC, no shielding
    • Take data: 2 hours
    • Install Pb shielding: 2 hours
    • Take data: 2 hours
    • Install 2 Pb shields: 2 hours
    • Take data: 2 hours
    • Restore nominal GlueX configuration: 4 hours.

Total time = 30 hours

  • Things to work out
    • Gas line manifold
    • Adjustable lead absorber
    • Alignment hardware
    • Complete structural analysis
    • Develop Detailed installation plan
    • Develop Design/operational/Maintenance Requirements

Minutes and Action Items

  • Reviewed minutes of last meeting
  • Bobby presented the configuration and the process was discussed - generally ok
  • Need to add platform to set lead on so 1 person can change it
  • Set up new meeting in 2 weeks