Revision as of 11:16, 10 July 2020
Meeting Time and Place =
Thursday July 09, 2020, 1:30pm Bluejeans https://bluejeans.com/735541157/3638?src=calendarLink
- Present - Elton, Dave, Bobby, Ilya, Eugene, Rory (remote)
Agenda
- Minutes from last meeting https://halldweb.jlab.org/wiki/index.php/June_18,_2020_CPP_Design_Meeting
- Upcoming run, possible testschedule Media:CPP_Tests_Aug2020.pdf
Assume that nominal the GlueX configuration consists of
- No Pb shielding
- DIRC installed
- Solenoid field at 1350 A
Screenshots of test layout
CPP Test Configuration
- With and without Pb shielding
- DIRC removed
- Solenoid field at 1350 A (no change)
- CPP test DAQ setup: 2 hrs
- Repeat measurement with nominal GlueX configuration: 2 hrs
- Configure experiment for CPP Test: 12 hours max
- Start with no DIRC, no shielding
- Take data: 2 hours
- Install Pb shielding: 2 hours
- Take data: 2 hours
- Install 2 Pb shields: 2 hours
- Take data: 2 hours
- Restore nominal GlueX configuration: 4 hours.
Total time = 30 hours
- Things to work out
- Gas line manifold
- Adjustable lead absorber
- Alignment hardware
- Complete structural analysis
- Develop Detailed installation plan
- Develop Design/operational/Maintenance Requirements
Minutes and Action Items
- Reviewed minutes of last meeting
- Bobby presented the configuration and the process was discussed - generally ok
- Need to add platform to set lead on so 1 person can change it
- Elton will obtain approval from Eugene to procure/build components
- Set up new meeting in 2 weeks