Difference between revisions of "July 09, 2020 CPP Design Meeting"

From GlueXWiki
Jump to: navigation, search
(Meeting Time and Place =)
(Agenda)
 
(13 intermediate revisions by 2 users not shown)
Line 1: Line 1:
= Meeting Time and Place ==
+
== Meeting Time and Place ==
 
Thursday July 09, 2020, 1:30pm
 
Thursday July 09, 2020, 1:30pm
 
Bluejeans https://bluejeans.com/735541157/3638?src=calendarLink
 
Bluejeans https://bluejeans.com/735541157/3638?src=calendarLink
Line 17: Line 17:
 
* DIRC removed
 
* DIRC removed
 
* Solenoid field at 1350 A (no change)
 
* Solenoid field at 1350 A (no change)
** CPP test DAQ setup: 2 hrs
+
 
** Repeat measurement with nominal GlueX configuration: 2 hrs
+
Screenshots of test layout [[media:CPP_Testconfig.jpg]]  [[media:CPP_Testconfig2.jpg]]
** Configure experiment for CPP Test: 12 hours
+
[[media:CPP_Testconfig3.jpg]]  [[media:CPP_Testconfig4.jpg]]
** Start with no DIRC, no shielding
+
[[media:CPP_Testconfig5.jpg]]  [[media:CPP_Testconfig6.jpg]]
** Take data: 2 hours
+
 
** Install Pb shielding: 2 hours
+
Possible sequence and times
** Take data: 2 hours
+
# CPP test DAQ setup: 2 hrs
** Install 2 Pb shields: 2 hours
+
# Repeat measurement with nominal GlueX configuration: 2 hrs
** Take data: 2 hours
+
# Configure experiment for CPP Test: 12 hours max
** Restore nominal GlueX configuration: 4 hours.
+
# Start with no DIRC, no shielding
 +
# Take data: 2 hours
 +
# Install Pb shielding: 2 hours
 +
# Take data: 2 hours
 +
# Install 2 Pb shields: 2 hours
 +
# Take data: 2 hours
 +
# Restore nominal GlueX configuration: 4 hours.
  
 
Total time = 30 hours
 
Total time = 30 hours
  
 +
The DIRC will have to be surveyed following the test.
 +
 +
Note by Elton: An updated schedule can be found in [[CPP Test 2020 - Schedule]]
 
* Things to work out
 
* Things to work out
 
** Gas line manifold
 
** Gas line manifold
Line 40: Line 49:
 
== Minutes and Action Items ==
 
== Minutes and Action Items ==
 
* Reviewed minutes of last meeting
 
* Reviewed minutes of last meeting
 +
* Bobby presented the configuration and the process was discussed - generally ok
 +
* Need to add platform to set lead on so 1 person can change it
 +
* Elton will obtain approval from Eugene to procure/build components
 
* Set up new meeting in 2 weeks
 
* Set up new meeting in 2 weeks

Latest revision as of 11:24, 15 July 2020

Meeting Time and Place

Thursday July 09, 2020, 1:30pm Bluejeans https://bluejeans.com/735541157/3638?src=calendarLink

  • Present - Elton, Dave, Bobby, Ilya, Eugene, Rory (remote)

Agenda

Assume that nominal the GlueX configuration consists of

  • No Pb shielding
  • DIRC installed
  • Solenoid field at 1350 A

CPP Test Configuration

  • With and without Pb shielding
  • DIRC removed
  • Solenoid field at 1350 A (no change)
Screenshots of test layout media:CPP_Testconfig.jpg  media:CPP_Testconfig2.jpg
media:CPP_Testconfig3.jpg  media:CPP_Testconfig4.jpg 
media:CPP_Testconfig5.jpg  media:CPP_Testconfig6.jpg

Possible sequence and times

  1. CPP test DAQ setup: 2 hrs
  2. Repeat measurement with nominal GlueX configuration: 2 hrs
  3. Configure experiment for CPP Test: 12 hours max
  4. Start with no DIRC, no shielding
  5. Take data: 2 hours
  6. Install Pb shielding: 2 hours
  7. Take data: 2 hours
  8. Install 2 Pb shields: 2 hours
  9. Take data: 2 hours
  10. Restore nominal GlueX configuration: 4 hours.

Total time = 30 hours

The DIRC will have to be surveyed following the test.

Note by Elton: An updated schedule can be found in CPP Test 2020 - Schedule

  • Things to work out
    • Gas line manifold
    • Adjustable lead absorber
    • Alignment hardware
    • Complete structural analysis
    • Develop Detailed installation plan
    • Develop Design/operational/Maintenance Requirements

Minutes and Action Items

  • Reviewed minutes of last meeting
  • Bobby presented the configuration and the process was discussed - generally ok
  • Need to add platform to set lead on so 1 person can change it
  • Elton will obtain approval from Eugene to procure/build components
  • Set up new meeting in 2 weeks