== Minutes and Action Items ==
 
== Minutes and Action Items ==
 
* Reviewed minutes of last meeting
 
* Reviewed minutes of last meeting
 +
* Discussed schedule, May happen as early as Mid August
 +
*Elton added empty target runs to plan
 +
* Test will start with 1 sheet of lead
 +
* Need to speak with Eugene about procurement priorities
 +
* Reviewd 3D models
  
 
* Set up new meeting in 2 weeks
 
* Set up new meeting in 2 weeks

Latest revision as of 06:59, 24 July 2020

Meeting Time and Place

Thursday July 23, 2020, 1:30pm Bluejeans https://bluejeans.com/735541157/3638?src=calendarLink

  • Present - Elton, Dave, Stephanie, Bobby, Ilya, Rory

Agenda

  • Things to work out
    • Gas line manifold
    • Adjustable lead absorber
    • Alignment hardware
    • Complete structural analysis
    • Develop Detailed installation plan
    • Develop Design/operational/Maintenance Requirements

Minutes and Action Items

  • Reviewed minutes of last meeting
  • Discussed schedule, May happen as early as Mid August
  • Elton added empty target runs to plan
  • Test will start with 1 sheet of lead
  • Need to speak with Eugene about procurement priorities
  • Reviewd 3D models
  • Set up new meeting in 2 weeks