(Created page with "= Meeting Time and Place == Thursday May 21, 2020, 1:30pm Bluejeans https://bluejeans.com/735541157/3638?src=calendarLink * Present - Elton, Dave, Stephanie, Llya, Rory (remo...") |
(→Minutes and Action Items) |
||
(6 intermediate revisions by the same user not shown) | |||
Line 11: | Line 11: | ||
* Design/Fab/Install schedule [[Media:CPP_install_schedule.pdf]] | * Design/Fab/Install schedule [[Media:CPP_install_schedule.pdf]] | ||
* 3D model - show progress | * 3D model - show progress | ||
− | * | + | * Upcoming run, possible tests [[Media:CPP_Tests.pdf]] |
* Things to work out | * Things to work out | ||
− | ** | + | ** Gas line manifold |
− | ** | + | ** Adjustable lead absorber |
** Procurement/installation schedule | ** Procurement/installation schedule | ||
** Alignment hardware | ** Alignment hardware | ||
** Electronics shielding [[Media:Muon_Chamber_Shielding.pdf]] | ** Electronics shielding [[Media:Muon_Chamber_Shielding.pdf]] | ||
− | |||
** Complete structural analysis | ** Complete structural analysis | ||
** Develop installation plan | ** Develop installation plan | ||
Line 25: | Line 24: | ||
== Minutes and Action Items == | == Minutes and Action Items == | ||
*Reviewed minutes of last meeting | *Reviewed minutes of last meeting | ||
− | + | * Discussed RF shielding over electronics board - they will be capped at the ends - UMASS will have them fabricated | |
+ | * The new chambers have a 2" hole in the center - this will be uncovered during installation | ||
+ | * The hole in all the iron pieces to be 8cm square with radius corners | ||
+ | * Hole in stationary lead to be 10cm square with radius corners | ||
+ | * Adjustable lead to be 14cm square with 8cm square hole,10cm thick. +/- 1cm movement and must be locally adjustable | ||
+ | * material for lead adjustment should be somewhat symmetrical and consistent all around | ||
+ | * we should plan on removing the vertical cable organizers since things are getting tight | ||
+ | * Discussed possible testing scenarios for the summer run - need to make decision on configurations | ||
+ | * Next meeting we can go over possible procurements | ||
* Set up new meeting in 2 weeks | * Set up new meeting in 2 weeks |
Latest revision as of 06:31, 4 June 2020
Meeting Time and Place =
Thursday May 21, 2020, 1:30pm Bluejeans https://bluejeans.com/735541157/3638?src=calendarLink
- Present - Elton, Dave, Stephanie, Llya, Rory (remote)
Agenda
- Minutes from last meeting https://halldweb.jlab.org/wiki/index.php/May_7,_2020_CPP_Design_Meeting#Minutes_and_Action_Items
- Overall description https://halldweb.jlab.org/DocDB/0041/004180/006/CPP_update_oct19.pdf
- FY2020 Procurement possibilities Media:CPP_Procurement_schedule.docx
- Design/Fab/Install schedule Media:CPP_install_schedule.pdf
- 3D model - show progress
- Upcoming run, possible tests Media:CPP_Tests.pdf
- Things to work out
- Gas line manifold
- Adjustable lead absorber
- Procurement/installation schedule
- Alignment hardware
- Electronics shielding Media:Muon_Chamber_Shielding.pdf
- Complete structural analysis
- Develop installation plan
- Develop Design/operational/Maintenance Requirements
Minutes and Action Items
- Reviewed minutes of last meeting
- Discussed RF shielding over electronics board - they will be capped at the ends - UMASS will have them fabricated
- The new chambers have a 2" hole in the center - this will be uncovered during installation
- The hole in all the iron pieces to be 8cm square with radius corners
- Hole in stationary lead to be 10cm square with radius corners
- Adjustable lead to be 14cm square with 8cm square hole,10cm thick. +/- 1cm movement and must be locally adjustable
- material for lead adjustment should be somewhat symmetrical and consistent all around
- we should plan on removing the vertical cable organizers since things are getting tight
- Discussed possible testing scenarios for the summer run - need to make decision on configurations
- Next meeting we can go over possible procurements
- Set up new meeting in 2 weeks