Difference between revisions of "May 27, 2010 Calorimetry"

From GlueXWiki
Jump to: navigation, search
(Tentative Agenda)
(Tentative Agenda)
Line 32: Line 32:
 
## [[FCAL Fabrication Readiness Review]]
 
## [[FCAL Fabrication Readiness Review]]
 
## To shashlyk or not to shashlyk. Options (Elton) see Table. Physics Impact, see [http://argus.phys.uregina.ca/cgi-bin/private/DocDB/ShowDocument?docid=1481 GlueX-doc-1481]
 
## To shashlyk or not to shashlyk. Options (Elton) see Table. Physics Impact, see [http://argus.phys.uregina.ca/cgi-bin/private/DocDB/ShowDocument?docid=1481 GlueX-doc-1481]
 +
## PbWO Insertion.  (Ashot) .  see [http://www.jlab.org/~gasparan/FCAL_INS/Gasparan_GlueX_Phys_meeting_May_24_2010.ppt]
 +
 
# BCAL
 
# BCAL
 
## Calorimeter input to PAC (Zisis)
 
## Calorimeter input to PAC (Zisis)

Revision as of 11:25, 27 May 2010

Teleconference Time: 11:00 a.m. EDT

  • ESNET and EVO session
  • Phone in CC F326 is 757-269-6337
  • Phone in the Regina Videoconference Suite is 306-585-4204
  • Phone only if requested:
    • +1-800-377-8846 : US
    • +1-888-276-7715 : Canada
    • +1-302-709-8424 : International
    • then enter participant code: 77438230# (remember the "#"). Phone line by request only.

Items for followup from previous meeting(s)

  1. Monitoring
    • Bcal: Testing to see if LED sources can be viewed by pmts on both sides of the module (UofR/UofA).
  2. Fcal
    • Draft agenda for Readiness Review (Elton and Matt)
    • Decision on rad hard detectors
  3. Bcal
    • Send copy of contract with Ross to JLab
    • Report on beam test data at small incidence angles.

Discussion of Options for Radiation-Hard Insert

Options for Radiation-Hard Insert

Tentative Agenda

  1. Announcements
  2. Review of Action Items
  3. Calibration/Monitoring (Zisis)
  4. FCAL
    1. Construction status
    2. FCAL Fabrication Readiness Review
    3. To shashlyk or not to shashlyk. Options (Elton) see Table. Physics Impact, see GlueX-doc-1481
    4. PbWO Insertion. (Ashot) . see [1]
  1. BCAL
    1. Calorimeter input to PAC (Zisis)
    2. Construction Status
    3. Lead: 6th order of 13cm-wide sheets
    4. Fibres: Media:FibresAttenLenShips1-12.png
    5. Npe corrected numbers: Media:ZoomedPage31.png and Media:ZoomedPage38.png
    6. USM MPPC test stand design update
  2. Simulations
  3. Other Updates
Elton and Fernando:

I corrected the dynamic range of BCAL according to Irina's results (from
gluex-doc-1474 note). The attachment contains "zoomed" plots from the note
pages 31 and 38 (for easy reading of the spectra edges).

Please use the corrected numbers for your references in the future.

Thank you,
Andrei

**********************************************************************
All Data from GlueX-doc-1474

         Shower                Upstream  Fig   Downstream  Fig
Eg (GeV)  Theta    Phi    Sum      Npe           Npe
0.06       105     gap   Inner-3   120     30     50         31(zoom)
0.06       105     gap   Inner-1    90     38     40         38(zoom)
2.5         12    center Inner-3  7500     15   17000        14
2.5         12    center Inner-1  5500     34   13000        33

Ratio (dynamic range)             62.5            340
                                   61            325

Minutes

Attendees: