Difference between revisions of "November 9, 2011 Tracking CDC/FDC"
From GlueXWiki
(→CDC Update) |
|||
Line 25: | Line 25: | ||
== CDC Update == | == CDC Update == | ||
+ | #As of yesterday 92 straws were strung in layer 28, this is the last of the straight layers. Next week we will move on to stereo, which will probably take a few days to prepare for, whilst the procedures are finalized and some extra assembly equipment modified (the alignment device). | ||
+ | #The stringing work is interleaved with testing tension in the wires installed the previous week and performing repeat measurements on older wires. | ||
+ | #Kait and Amy have been manufacturing hook up wires. | ||
+ | #Gary is busy manufacturing the small pieces required for the swiss cheese plate. |
Revision as of 12:25, 9 November 2011
_TOC__
Meeting Time and Place
Wednesday November 9, 2011 at 11:00am At Jefferson Lab, the meeting will be held in F326
Connections
To connect from the outside, please use ESNET
- ) ESNET: 8542553
- )To connect by telephone, dial:
- You can look up toll-free number at http://www.readytalk.com/intl
- US and Canada: (866)740-1260 (toll free)
- International: (303)248-0285 (toll call)
- enter access code followed by the # sign: 3421244#
Agenda
- Announcements
- FDC Update logbook
- CDC Update
Minutes
Participants: Curtis, Naomi, Beni, Simon, Lubomir, Elton, Mark, Dave
FDC Update
CDC Update
- As of yesterday 92 straws were strung in layer 28, this is the last of the straight layers. Next week we will move on to stereo, which will probably take a few days to prepare for, whilst the procedures are finalized and some extra assembly equipment modified (the alignment device).
- The stringing work is interleaved with testing tension in the wires installed the previous week and performing repeat measurements on older wires.
- Kait and Amy have been manufacturing hook up wires.
- Gary is busy manufacturing the small pieces required for the swiss cheese plate.