Organization

  • Time: 4 pm EST
  • Connecting: detailed instructions are here
  • Conference id: 536076821

References

Action Items

  • Send Todd a geometry of tagger area, including the mapped tagger magnet field, for GEANT simulations (Richard). Richard is working to update the defined geometry based on a drawing received from Tim, Richard will add field map from Dan Sober
  • Estimate rates and ranges of parameters needed for the photon beam tuning (Todd for accelerator; Elton, Hovanes, Eugene, Alexandre for Hall D)
    • Need rates for profiler, start counter, ps

Agenda

  1. Announcements
  2. Recommendations from ERR Report
  3. Aug 8 Photon Beam Commissioning Review Final Report
  4. ARR presentations
  5. Accelerator and Hall D Interface Document - needs to be finalized.
  6. Update on Photon Commissioning (Alexandre)
  7. RadCon update
  8. Other business

Minutes

Attending: