Difference between revisions of "Photon Beam Commissioning Discussion Oct 8, 2014"
From GlueXWiki
(→Action Items) |
(→Action Items) |
||
Line 15: | Line 15: | ||
** Need rates for profiler, start counter, ps | ** Need rates for profiler, start counter, ps | ||
* Complete the tagger drawing with the expected configuration for the fall running, including all shielding. (Tim, Chuck, Elton) | * Complete the tagger drawing with the expected configuration for the fall running, including all shielding. (Tim, Chuck, Elton) | ||
− | * Screen of beam parameters for Hall D (Hovanes) | + | *[[media:Gluex_overview_draft.jpg | Screen of beam parameters for Hall D]] (Hovanes) |
* Feedback on accelerator on latest ICD draft (Michael, Todd) | * Feedback on accelerator on latest ICD draft (Michael, Todd) | ||
* List of variables from radiation monitors to Pavel (Hovanes and Alexandre) | * List of variables from radiation monitors to Pavel (Hovanes and Alexandre) |
Revision as of 15:46, 8 October 2014
Organization
- Time: 4:00 pm EST
- Connecting: detailed instructions are here
- H.323 ip address: 199.48.152.152
- web browser: https://bluejeans.com/536076821
- phone: 408-740-7256 or 888-240-2560
- Conference id: 536076821
References
Action Items
- Estimate rates and ranges of parameters needed for the photon beam tuning (Todd for accelerator; Eugene, Alexandre for Hall D)
- Need rates for profiler, start counter, ps
- Complete the tagger drawing with the expected configuration for the fall running, including all shielding. (Tim, Chuck, Elton)
- Screen of beam parameters for Hall D (Hovanes)
- Feedback on accelerator on latest ICD draft (Michael, Todd)
- List of variables from radiation monitors to Pavel (Hovanes and Alexandre)
Agenda
- Announcements
- Accelerator and Hall D Interface Document - update
- Update on Photon Commissioning (Alexandre)
- Beam Simulations
- RadCon update
- Other business
Minutes
Attending: