== Agenda ==
 
== Agenda ==
 
# Announcements
 
# Announcements
 +
# ARR3 Recommendations
 +
#* [http://www.jlab.org/Hall-D/halld_secure/reviews/ARR3_Aug2014/ARR_Phase_3_Report_Aug_2014.pdf ARR3 Report]
 
# Accelerator and Hall D Interface Document - update
 
# Accelerator and Hall D Interface Document - update
 
# Update on Photon Commissioning (Alexandre)
 
# Update on Photon Commissioning (Alexandre)

Revision as of 15:55, 8 October 2014

Organization

  • Time: 4:00 pm EST
  • Connecting: detailed instructions are here
  • Conference id: 536076821

References

Action Items

  • Estimate rates and ranges of parameters needed for the photon beam tuning (Todd for accelerator; Eugene, Alexandre for Hall D)
    • Need rates for profiler, start counter, ps
  • Complete the tagger drawing with the expected configuration for the fall running, including all shielding. (Tim, Chuck, Elton)
  • Screen of beam parameters for Hall D (Hovanes)
  • Feedback on accelerator on latest ICD draft (Michael, Todd)
  • List of variables from radiation monitors to Pavel (Hovanes and Alexandre)

Agenda

  1. Announcements
  2. ARR3 Recommendations
  3. Accelerator and Hall D Interface Document - update
  4. Update on Photon Commissioning (Alexandre)
  5. Beam Simulations
  6. RadCon update
  7. Other business

Minutes

Attending: