Organization

  • Time: 4 pm EST
  • Connecting: detailed instructions are here
  • Conference id: 536076821

References

Action Items

  • Estimate rates and ranges of parameters needed for the photon beam tuning (Todd for accelerator; Elton, Hovanes, Eugene, Alexandre for Hall D)
    • Need rates for profiler, start counter, ps
  • Richard will provide a "sacrificial" board with 30 SiPMs to register neutron damage during initial electron beam tune.
  • Hovanes is preparing photomultipliers that can be used to measure beam loss along the beamline.
  • Complete the tagger layout with the expected configuration for the fall running, including all shielding. (Tim, Chuck, Elton)

Agenda

  1. Announcements
  2. Comments on ARR
  3. Accelerator and Hall D Interface Document - update
  4. Update on Photon Commissioning (Alexandre)
  5. Beam Simulations
  6. RadCon update
  7. Other business

Minutes

Attending: