(Wednesday, April 13)
Line 7: Line 7:
 
#* Beam went down at 7am Tuesday for SL work followed by 5th pass separator test. It was gone until~2am.
 
#* Beam went down at 7am Tuesday for SL work followed by 5th pass separator test. It was gone until~2am.
 
#* [https://logbooks.jlab.org/entry/3398430 Ion chambers not reporting since 3/27]
 
#* [https://logbooks.jlab.org/entry/3398430 Ion chambers not reporting since 3/27]
 +
#* Hall-A getting 5-pass beam
 +
#* Beam studies starting ~8am Thursday
 +
#* Hall-B becomes priority 15:00 Friday
 
# Hall-D/GlueX items
 
# Hall-D/GlueX items
 
#* [https://logbooks.jlab.org/entry/3397757 Solenoid Incident]
 
#* [https://logbooks.jlab.org/entry/3397757 Solenoid Incident]
Line 14: Line 17:
 
#* [https://logbooks.jlab.org/entry/3398268 Occupancy Plots]
 
#* [https://logbooks.jlab.org/entry/3398268 Occupancy Plots]
 
#* Latest scans: [https://logbooks.jlab.org/entry/3398296 5C11,5C11B] , [https://logbooks.jlab.org/entry/3398305 Hall-D harp scan]
 
#* Latest scans: [https://logbooks.jlab.org/entry/3398296 5C11,5C11B] , [https://logbooks.jlab.org/entry/3398305 Hall-D harp scan]
 +
#* [https://logbooks.jlab.org/entry/3398437 Current fluctuations]
 
#* other systems?
 
#* other systems?
 
# Run Plan
 
# Run Plan

Revision as of 08:45, 13 April 2016

Wednesday, April 13

  1. Accelerator Status
    • Beam went down at 7am Tuesday for SL work followed by 5th pass separator test. It was gone until~2am.
    • Ion chambers not reporting since 3/27
    • Hall-A getting 5-pass beam
    • Beam studies starting ~8am Thursday
    • Hall-B becomes priority 15:00 Friday
  2. Hall-D/GlueX items
  3. Run Plan
  4. Offline analysis?
  5. AOB?

https://logbooks.jlab.org/entry/3398268

Tuesday, April 12

  1. Accelerator Status
    • Beam went down at 7am for work in SL.
    • Accelerator will investigate going back to 5th pass separation. If possible, Hall-A will use 5 pass beam. If not, they will use 4 pass.
    • Beam expected back late during swing shift or early owl
  2. Hall-D/GlueX items
  3. Run Plan
  4. Offline analysis?
  5. AOB?

Monday, April 11

  1. Accelerator Status
    • Beam went down at 7am for radcon survey of SL
    • Hall-A going to 2 pass (will take a couple of hours. Estimate is to come back ~10am)
      • "... blind ..."
  2. Hall-D/GlueX items
  3. Run Plan
  4. Offline analysis?
  5. AOB?