Run Planning Meeting Notes, April 11-April 18, 2016

From GlueXWiki
Revision as of 23:42, 12 April 2016 by Davidl (Talk | contribs)

Jump to: navigation, search

Wednesday, April 13

  1. Accelerator Status
    • Beam went down at 7am Tuesday for SL work followed by 5th pass separator test. It was gone until ...
  2. Hall-D/GlueX items
  3. Run Plan
  4. Offline analysis?
  5. AOB?

https://logbooks.jlab.org/entry/3398268

Tuesday, April 12

  1. Accelerator Status
    • Beam went down at 7am for work in SL.
    • Accelerator will investigate going back to 5th pass separation. If possible, Hall-A will use 5 pass beam. If not, they will use 4 pass.
    • Beam expected back late during swing shift or early owl
  2. Hall-D/GlueX items
  3. Run Plan
  4. Offline analysis?
  5. AOB?

Monday, April 11

  1. Accelerator Status
    • Beam went down at 7am for radcon survey of SL
    • Hall-A going to 2 pass (will take a couple of hours. Estimate is to come back ~10am)
      • "... blind ..."
  2. Hall-D/GlueX items
  3. Run Plan
  4. Offline analysis?
  5. AOB?