(Thursday, Dec 12 at 08:45)
(Thursday, Dec 12 at 08:45)
Line 44: Line 44:
 
#* Hall Work
 
#* Hall Work
 
#** Relocate GEM/TRD
 
#** Relocate GEM/TRD
#** Installing additional flash module
+
#** Installing additional flash module (Sasha)
 
#* Setting up high current test? (Sasha)
 
#* Setting up high current test? (Sasha)
 +
#* TOF: Beni
 +
#* Profiler & FCal prototype: Ashark & Vlad
 
# Plan for later
 
# Plan for later
 
#* Spin dance no longer scheduled
 
#* Spin dance no longer scheduled

Revision as of 09:38, 13 December 2019

Thursday, Dec 12 at 08:45

  1. Last 24h:
  2. Issue:
    • DAQ crash
      • DAQ issues (of manifest variety)
    • DIRC reference signal found in the stand alone configuration
    • Alarms for FDC HV
    • TAGM translation table
    • Data corruption issue in the beginning of the run.
    • rcdb event number issue.
  3. Task for today
    • Setting up high current test (Sasha)
    • CPP test crash (Dave)
  4. Plan for later

Thursday, Dec 12 at 08:45

  1. Last 24h:
    • DIRC Gem data beam center configuration collected additional 5M trigger (6m triggers in total).
    • The CPP test (1 hour) run was completed
    • Overnight collected ~3 hours of DIRC commissioning data.
      • Diamond 0/90 Para/Perp & AMO at 150nA current, coherent peak at 8.6 GeV
    • 30 mins Raw mode data taken:
  2. Issues:
  3. Task for today
    • Hall Work
      • Relocate GEM/TRD
      • Installing additional flash module (Sasha)
    • Setting up high current test? (Sasha)
    • TOF: Beni
    • Profiler & FCal prototype: Ashark & Vlad
  4. Plan for later