(Friday, Dec 6 at 08:45)
(Friday, Dec 6 at 08:45)
Line 46: Line 46:
 
#* CDC & TOF scans
 
#* CDC & TOF scans
 
#* DIRC commissioning field-on
 
#* DIRC commissioning field-on
 +
#* Opp access request from Sasha 30 mins to replace fcal fadcs
 
# Plan for later  
 
# Plan for later  
 
#*  [https://halldweb.jlab.org/wiki/index.php/Run_Coordination_Meetings:Fall2019_Run#Runplan Alexandre's comprehensive runplan] now at #5
 
#*  [https://halldweb.jlab.org/wiki/index.php/Run_Coordination_Meetings:Fall2019_Run#Runplan Alexandre's comprehensive runplan] now at #5

Revision as of 18:02, 5 December 2019

<- Back to Run Coordination Meetings:Fall2019 Run

Thursday, Dec 5 at 08:45

  1. Last 24h:
    • Straight tracks during the day, Justin & Sean working to debug recon and analyze the data
    • Sean got the general detector checkout done.
    • Sasha did the PS threshold scan and set up the PS trigger for Richard's uscope scan
    • Sasha set up trigger config for straight tracks excluding uscope so Richard can work independently
    • Richard's uscope scans half done, interrupted by ghost PSS button press from tagger hall, no beam from approx 9pm - 1am?
    • Lubomir's logentry
  2. Issues
    • Solenoid alarm
    • PSS fault
    • GEM cable or module swap
  3. Plan for today
    • After the meeting (TBD Justin), move GEM to position 2, fix electronics problem, then take more data until ~4pm?
    • Move GEM to position 3, then take more data until ~6am Friday?
  4. Plan for later
  5. Notes from this meeting.
    • Also need to check the GEM readout config
    • Beam time request from David for CPP
    • Radiation levels report from Alexandre
    • Repeated alarms for TAGH 151

Friday, Dec 6 at 08:45

  1. Last 24h:
  2. Issues
  3. Plan for today
    • Empty target, ramp solenoid while Richard does tagger accidentals measurement
    • Fill target.
    • CDC & TOF scans
    • DIRC commissioning field-on
    • Opp access request from Sasha 30 mins to replace fcal fadcs
  4. Plan for later
  5. Notes from this meeting.