Difference between revisions of "Run Planning Meeting Notes, December 2 - December 8, 2021"
From GlueXWiki
(→Thursday December 2) |
(→Thursday December 2) |
||
Line 1: | Line 1: | ||
− | =Thursday December 2= | + | =Friday, December 3= |
+ | #Last 24h: | ||
+ | #* | ||
+ | #Issues: | ||
+ | #* | ||
+ | # [https://halldweb.jlab.org/wiki/index.php/SRC/CT_Run_Plan Plan:] | ||
+ | #* run on carbon at 150nA´ | ||
+ | #* Rotate the radiators and use both configurations | ||
+ | ##* Stop the beam ALWAYS before changing the radiator configuration (even with the same radiator). Between radiator change (0/90 <--> 35/145) ALWAYS ask MCC to insert the dumplette. | ||
+ | # Analysis update | ||
+ | |||
+ | =Thursday, December 2= | ||
#Last 24h: | #Last 24h: | ||
#* Established beam last night before midnight. | #* Established beam last night before midnight. |
Revision as of 14:23, 2 December 2021
Friday, December 3
- Last 24h:
- Issues:
- Plan:
- run on carbon at 150nA´
- Rotate the radiators and use both configurations
- Stop the beam ALWAYS before changing the radiator configuration (even with the same radiator). Between radiator change (0/90 <--> 35/145) ALWAYS ask MCC to insert the dumplette.
- Analysis update
Thursday, December 2
- Last 24h:
- Established beam last night before midnight.
- Harp scan extrapolation looks to be focused a bit differently than before. PS rates seemed around 3.2kHz as before with 150nA beam so we kept this.
- Radiation levels at 50nA acceptable.
- Continued production on C target at 150nA. Beam not available for most of Early Riser shift so far.
- Issues:
- Plan:
- run on carbon at 150nA´
- Rotate the radiators and use both configurations
- Stop the beam ALWAYS before changing the radiator configuration (even with the same radiator). Between radiator change (0/90 <--> 35/145) ALWAYS ask MCC to insert the dumplette.
- Analysis update