Difference between revisions of "Run Planning Meeting Notes, Jan 23-Jan 29, 2020"

From GlueXWiki
Jump to: navigation, search
(Thursday, January 23 at 08:45)
(Thursday, January 23 at 08:45)
Line 21: Line 21:
 
#* Production
 
#* Production
 
#* DOE tour in Hall B/C (8:00 - 12:00?)
 
#* DOE tour in Hall B/C (8:00 - 12:00?)
 +
#* Spin dance (12:00?)
 
# Plan for later
 
# Plan for later
 
#* CCAL anode study?
 
#* CCAL anode study?
 
#* Alternative diamond alignment
 
#* Alternative diamond alignment
 
#* ST trigger?
 
#* ST trigger?

Revision as of 10:08, 23 January 2020

Trigger Spreadsheet

Trigger Counter

Thursday, January 23 at 08:45

  1. Last 24 hours
    • Various accelerator problems: Arc PS, Injector, Cavity HV [1]
    • Check-out of PS, TagM, TagH, ST after timing window shift [2], [3]
    • Harp Scan [4]
    • Continue production with 250nA beam current
  2. Issues
    • Timing shifts after firmware update: [5]
    • PS Timing Window? [6], [7]
    • CDC inner region [8], [9]
    • DIRC@Rootspy glitches [10],[11]
    • Frozen PS/Main trigger rates [12], [13]
    • Update reference plots! [14], [15]
  3. Reports:
  4. Tasks for today
    • Production
    • DOE tour in Hall B/C (8:00 - 12:00?)
    • Spin dance (12:00?)
  5. Plan for later
    • CCAL anode study?
    • Alternative diamond alignment
    • ST trigger?