(Tuesday, January 25 at 08:45)
(Tuesday, January 25 at 08:45)
Line 8: Line 8:
 
# Issues
 
# Issues
 
#* TOF point disappearance after window shift [https://logbooks.jlab.org/entry/3772058], [https://logbooks.jlab.org/entry/3772122]
 
#* TOF point disappearance after window shift [https://logbooks.jlab.org/entry/3772058], [https://logbooks.jlab.org/entry/3772122]
 +
#* Missing DIRC blocks [https://logbooks.jlab.org/entry/3772139]
 
#* Event size increase due to CCal [https://logbooks.jlab.org/entry/3772097]
 
#* Event size increase due to CCal [https://logbooks.jlab.org/entry/3772097]
 
# Reports
 
# Reports

Revision as of 16:40, 27 January 2020

Trigger Spreadsheet

Trigger Counter

Tuesday, January 25 at 08:45

  1. Last 24 hours
    • First day of production with 350nA beam current!
  2. Issues
    • TOF point disappearance after window shift [1], [2]
    • Missing DIRC blocks [3]
    • Event size increase due to CCal [4]
  3. Reports
  4. Plans for today
    • No beam study / RF recovery planned
    • Diamond alignment later this week

Monday, January 24 at 08:45

  1. Last 72 hours
    • Mostly Production with 250nA beam current
    • Empty target runs with 250nA (71533) and 350nA (71532) on Friday
    • Harp Scan on Sunday [5]
    • CCal Anode Tests on Sunday evening (Sasha) [6]
  2. Issues
  3. Reports
  4. Tasks for the today
    • Increase beam current to 350nA
      • Switch off low-energy TagH counters (new EPICS configuration file) [14]
    • No beam study / RF recovery planned
    • Diamond alignment later this week

Friday, January 24 at 08:45

  1. Last 24 hours
    • Production with 250nA beam current
    • Beam current and position [15], [16]
  2. Issues
    • Frozen total PS/FCal rates fixed (Hovanes)
    • Goniometer image missing [17]
  3. Reports:
  4. Tasks for the today and the weekend:
    • Empty target run after the meeting if beam is taken away
    • PS Timing Studies (Friday)?
    • Production
    • CCAL anode study (Saturday)?
  5. Monday:
    • Increase beam current to 350nA

Thursday, January 23 at 08:45

  1. Last 24 hours
    • Various accelerator problems: Arc PS, Injector, Cavity HV [19]
    • Check-out of PS, TagM, TagH, ST after timing window shift [20], [21]
    • Harp Scan [22]
    • Continue production with 250nA beam current
  2. Issues
  3. Reports:
  4. Tasks for today
    • Production
    • DOE tour in Hall B/C (8:00 - 12:00?)
    • Spin dance (12:00?)
  5. Plan for later
    • CCAL anode study?
    • Alternative diamond alignment
    • ST trigger?