Run Planning Meeting Notes, July 28- August 3, 2022
From GlueXWiki
Back to Run Coordination Meetings:Summer2022
Meeting are via ZoomGov: connect (Meeting ID: 160 199 0060 / Passcode 8394)
Hall D counting room white board
Contents
Monday August 1
Past 72 hours
- Fri: ~3.9B triggers
- Sat: ~3.0B triggers
- Sun: >2.5B triggers
- Half-wave plate moved out on Sunday afternoon
- RootSpy issues and here
- Counting house not host of zoom meeting log entry
- Gas shed key missing
Shift Reports
Reports
Plans
- Switch to empty target during accelerator down time (>=2hr)
- Production running on empty target for 1.5 days
Sunday July 31
Shift Reports
Saturday July 30
Shift Reports
Friday July 29
Past 24 hours
- Thanks Rory for previous RC shift
- Beam studies during Day shift
- Mark D.: Safety walk-through
- Beni: CTOF repair, Mark: gain equalization
- Mark+Malte: FCAL repairs
- Beam returned ~16:30
- ~2.0B triggers
Shift Reports
Reports
Plans
- Long mode run 1/2 hour
- Production running on Pb through weekend
- No meetings over weekend
Thursday July 28
Past 24 hours
- Beam returned ~ noon
- Harp scans
- Production data taking ~ 13:30
- ~2.9B triggers
Shift Reports
Reports
Plans
- Beam Studies today
- Hall-D Walk through - Mark D.
- CTOF PMT Repair - Beni Z.
- Production running on Pb when beam returns