== Monday, March 9 ==
 +
#Last 72 hours
 +
#*
 +
#* Mostly production evening and overnight
 +
# Reports/Issues
 +
#* Rates instability: requested other Hall beam off and Harp Scan during "dip" in rate on Friday evening.
 +
#**
 +
#** Since then the rate has been ~stable
 +
#* Multiple processes running to different edge fitting scripts caused fluctuations i (Mark D)
 +
#** New edge fitting script in use to better determine edge and width (Mark D)
 +
#* Monitoring:
 +
#** &rho; and &omega; yield/trigger back to nominal values (Alex)
 +
#* [https://logbooks.jlab.org/entry/3798088 something weird] is fixed, was a bad ADC channel (Beni)
 +
#* [https://logbooks.jlab.org/entry/3797335 Bad data from CAEN HV] and intermittent LINK alarms (Hovanes)
 +
# Run Plan (Friday + Weekend)
 +
#* Production
 +
# Longer term
 +
#* Hall C down for configuration change 3/13-3/20.  Good opportunity for low current TAC run.
  
 
==  Friday, March 6 ==  
 
==  Friday, March 6 ==  

Revision as of 07:15, 9 March 2020

<- Back to Run Coordination Meetings:Fall2019 Run Integrated trigger count

Monday, March 9

  1. Last 72 hours
    • Mostly production evening and overnight
  2. Reports/Issues
    • Rates instability: requested other Hall beam off and Harp Scan during "dip" in rate on Friday evening.
      • Since then the rate has been ~stable
    • Multiple processes running to different edge fitting scripts caused fluctuations i (Mark D)
      • New edge fitting script in use to better determine edge and width (Mark D)
    • Monitoring:
      • ρ and ω yield/trigger back to nominal values (Alex)
    • something weird is fixed, was a bad ADC channel (Beni)
    • Bad data from CAEN HV and intermittent LINK alarms (Hovanes)
  3. Run Plan (Friday + Weekend)
    • Production
  4. Longer term
    • Hall C down for configuration change 3/13-3/20. Good opportunity for low current TAC run.

Friday, March 6

  1. Last 24 hours
    • Limited beam yesterday morning, followed by Hall access for Solenoid VCL work (Scot/Mark)
    • Steady production evening and overnight
  2. Reports/Issues
  3. Run Plan (Friday + Weekend)
    • May be some additional (short) injector tuning (A2 interception) today to keep Hall A's charge asymmetry down.
    • Production
  4. Longer term
    • Hall C down for configuration change 3/13-3/20. Good opportunity for low current TAC run.

Thursday, March 5

  1. Last 24 hours
  2. Reports/Issues
  3. Run Plan
    • Opportunistic access for solenoid work in parallel with injector tuning (1:00 pm)
    • Production