(Monday, Dec 4 at 8:45)
Line 42: Line 42:
 
==Monday, Dec 4 at 8:45 ==
 
==Monday, Dec 4 at 8:45 ==
  
#* Target installation Plan
+
# Target installation Plan
#* TAGM trigger issue (Richard)
+
# TAGM trigger issue (Richard)
 +
https://logbooks.jlab.org/entry/3633836

Revision as of 12:28, 3 December 2018

Friday, Nov 30 at 8:45

  1. Comp Cal installation
    • Completed at 6pm yesterday
  2. First sight of beam (by Comp Cal): https://logbooks.jlab.org/entry/3633247
  3. Swing and Overnight Running
    • 15 nA on Al V-wire (full running condition).
    • Lost beam around 2am (due to radiation damaged valve position sensor).
  4. FCAL is down:
  5. Run Plan:
  6. Cryo


Monday, Dec 3 at 8:45

  1. Comp Cal Status
    • Friday: cell-by-cell calibration
    • Friday overnight: successful TAC run
    • Saturday: completed cell-by-cell calibration
    • Saturday overnight: no beam / TAC rate issue (due to beam characteristic change).
    • Sunday: completed voltage matching
    • Sunday overnight: voltage crosscheck data taken
    • Data ready?
  2. Target
    • Be target installation (tentative date is Thursday)
    • LH2 Cooling and when?
      • Empty target data during the target colling process?
  3. Accelerator
    • Beam study 9am-2pm
    • Energy change next Monday
  4. Planned hall access:
    • Alex: hall tour at 1:30
    • Sean/Stuart: checking the cable for the tagger hodoscope (not scheduled)
    • Hall tour tomorrow?
  5. Other idea of using the low current beam
    • Ken: The coherent peak test near the tagger hodoscope low energy boundary (preferably after the energy change) with ~2nA current


Monday, Dec 4 at 8:45

  1. Target installation Plan
  2. TAGM trigger issue (Richard)

https://logbooks.jlab.org/entry/3633836