Difference between revisions of "Solenoid Coil Test in Test Lab"

From GlueXWiki
Jump to: navigation, search
m
m
Line 34: Line 34:
 
** Have or can borrow all material moving equipment, or will contract out to rigging firm.
 
** Have or can borrow all material moving equipment, or will contract out to rigging firm.
 
** Have or can borrow all tools needed.
 
** Have or can borrow all tools needed.
 +
** Controls racks coming from Randy H or from computer center.
  
  
Line 42: Line 43:
 
*** Design piping to vent N2.
 
*** Design piping to vent N2.
 
*** Design warm and cold He supply/return systems, LN2 supply system.
 
*** Design warm and cold He supply/return systems, LN2 supply system.
** Order warm He and N2 piping - ?
 
 
** Retrieve rails from IU - ?
 
** Retrieve rails from IU - ?
 +
** Get three racks from Randy H or from CC - Mark S and Elliott W
 
** Determine cryogen supply/return needs - George
 
** Determine cryogen supply/return needs - George
** Arrange for cryogen supply/return with Dana Arenius - George and Elliott
+
** Arrange for cryogen supply/return with Dana Arenius (and Kelly Dixon?)- George and Elliott
  
  
Line 53: Line 54:
  
 
* '''To Do:'''
 
* '''To Do:'''
** Verify we have all cryo transfer lines and U-tubes - Mark S
+
** Order cryo can - George
 +
** Verify all cryo transfer lines and U-tubes are available on site - Mark S
 
** Verify we can borrow heat exchanger from Hall A - George
 
** Verify we can borrow heat exchanger from Hall A - George
 +
** Get heat exchanger - Mark S
 +
** Order remaining piping - ?
  
  

Revision as of 14:52, 18 June 2009

Notes and to-do lists for the solenoid coil tests this summer and fall.


Test Area

  • Notes:
    • Wayne is designing overall layout.
    • Area in the test lab is 20'6" x 25'9", currently filled with coils and coil parts.
    • May be able to get space in adjacent areas (QWeak construction and SRF cavity storage areas).
    • May need extra space for large power supply (6' x 5') and switch, and to avoid placing controls racks in large B field.
    • Must maintain clear areas around racks and power supply, and cannot block pedestrian walkways.
    • Platform is 172" x 160", cryo can will sit on top.
    • Platform must be removed to swap coils, and all connections to it must be broken.
    • Area has two cranes, but need both (and spreader bar) to lift heaviest yoke (45 tons).
    • Need come-alongs and anchors to move yokes and coils along rails.
    • Some areas will need to be roped off due to high B fields (> 5 Gauss, for pacemakers)


  • To Do:
    • Look into getting space in adjacent areas - George
    • Look into possibility of locating computer in control room - Elliott
    • Distribute Floyd's B field map for single coil, no cladding - George
    • Determine location of all components - Wayne
    • Investigate sensitivity of electronic equipment to B fields - Elliott
    • Find spreader bar - George
    • Determine areas to be roped off due to high B field - Floyd, George


Infrastructure

  • Notes:
    • Platform borrowed from Hall A.
    • Rails currently at IU.
    • Have or can borrow all material moving equipment, or will contract out to rigging firm.
    • Have or can borrow all tools needed.
    • Controls racks coming from Randy H or from computer center.


  • To Do:
    • Produce overall system diagram - George
    • Design structures and mechanical components, route cables and cryo piping, etc. - Wayne
    • Arrange for piping designer - George
      • Design piping to vent N2.
      • Design warm and cold He supply/return systems, LN2 supply system.
    • Retrieve rails from IU - ?
    • Get three racks from Randy H or from CC - Mark S and Elliott W
    • Determine cryogen supply/return needs - George
    • Arrange for cryogen supply/return with Dana Arenius (and Kelly Dixon?)- George and Elliott


Components

  • Notes:
  • To Do:
    • Order cryo can - George
    • Verify all cryo transfer lines and U-tubes are available on site - Mark S
    • Verify we can borrow heat exchanger from Hall A - George
    • Get heat exchanger - Mark S
    • Order remaining piping - ?


Programming

  • Notes:
    • Mark W will do all programming.
    • Can borrow lots of code from Steve Lassiter and co.
    • Single computer will perform all control and monitoring tasks.
  • To Do:
    • Install new memory in controls computer - Elliott and Mark W
    • Purchase new software licenses - Elliott
    • Install all software on controls computer - Mark W
    • Borrow code from Steve Lassiter - Mark W


Staging

  • Notes:
    • Will instrument controls racks in F117, then move to Test Lab.
    • Will instrument for final 4-coil system.
  • To Do:
    • Rearrange F117 - Mark S and Beni
    • Get and move 3 racks into F117 - Mark S


Reviews

  • Notes:
    • Micro-review of PLC vendor choice completed, waiting for report.
    • Need cryo, electrical, mechanical, and operations reviews.


  • To Do:
    • Write thank-you letter to Jonathan Creel and Omar Garza for participating in PLC vendor review - Elliott
    • Write appropriate documentation - George, Mark S, Wayne and Elliott
    • Set up all reviews - George and Elliott


Construction

  • Notes:
    • Do we have enough manpower?


  • To Do:


Coil Tests

  • Notes:
    • Verify correct operation of all coils.
    • Determine stresses up to full current (1600 A).
    • Will take about one month per coil.
    • Will take a few days to cool down a single coil.


  • To Do:
    • Create test plan - George