Notes and to-do lists for the solenoid coil tests this summer and fall.


Test Area

  • Notes:
    • Area is in the test lab, footprint 20'6" x 25'9", currently filled with coils and coil parts.
    • May be able to get space in adjacent area (QWeak construction and SRF cavity storage areas).
    • Need space for large power supply (6' x 5') and to avoid placing controls racks in large B field.
    • Must maintain clear areas around racks, power supply and cannot block pedestrian areas.
    • Platform is 172" x 160".
    • Need to design piping to vent N2.
    • Need to design piping for warm and cold He, LN2.
  • To Do:
    • Look into getting space in adjacent areas - George
    • Look into possibility of locating computer in control room - Elliott
    • Distribute Floyd's B field map for single coil, no cladding - George
    • Determine location of all components - Wayne
    • Arrange for piping designer - George
    • Investigate sensitivity of electronic equipment to B fields - Elliott


    • Verify we have all cryo transfer lines and U-tubes - Mark S
    • Verify we can borrow heat exchanger from Hall A - George
    • Order warm He and N2 piping - ?


Infrastructure

  • Notes:
  • To Do:


Components

  • Notes:
  • To Do:


Staging

  • Notes:
  • To Do:


Reviews

  • Notes:
    • Micro-review of PLC vendor choice completed, waiting for report.
  • To Do:
    • Write thank-you letter to Jonathan Creel and Omar Garza for participating in PLC vendor review.