Solenoid Coil Test in Test Lab

From GlueXWiki
Revision as of 10:03, 19 June 2009 by Wolin (Talk | contribs)

Jump to: navigation, search

Notes and to-do lists for the solenoid coil tests this summer and fall.


Test Area

  • Notes:
    • Area in the test lab is 20'6" x 25'9", currently filled with coils and coil parts.
    • Bob Bennett is Test Lab "space czar."
    • Wayne is designing overall layout.
    • May be able to get space in adjacent areas (QWeak construction and SRF cavity storage areas).
    • May need extra space for large power supply (6' x 5', 5' H, 5000 lbs) and switch, and to avoid placing controls racks in large B field.
    • Must maintain clear areas around racks and power supply, and cannot block pedestrian walkways.
    • Platform is 172" x 160", cryo can will sit on top.
    • Platform must be removed to swap coils, and all connections to it must be broken.
    • Area has two 25T cranes, but need both (and spreader bar) to lift heaviest yoke (45 tons).
    • Need come-alongs and anchors to move yokes and coils along rails.
    • Some areas will need to be roped off due to high B fields (> 5 Gauss, for pacemakers)
    • May need to remove some fences.


  • To Do:
    • Look into getting space in adjacent areas - George
    • Look into possibility of locating computer in control room (contact Joe Preble, Mark Drury)- Elliott
    • Distribute Floyd's B field map for single coil, no cladding - George
    • Determine location of all components - Wayne
    • Investigate sensitivity of electronic equipment to B fields - Elliott
    • Find spreader bar - George
    • Determine areas to be roped off due to high B field - Floyd, George
    • Enable building access for everyone.


Infrastructure

  • Notes:
    • Platform borrowed from Hall A.
    • Rails currently at IU.
    • Have or can borrow all material moving equipment, or will contract out to rigging firm.
    • Have or can borrow all tools needed.
    • Controls racks coming from Randy H or from computer center.
    • Need 60 W liquid He, Test Lab supply capable of 500 W, but share with Cryo group.
    • Must account for magnetic forces on all structures, perhaps as much as 20-30 Gauss static B field.


  • To Do:
    • Produce overall system diagram - George
    • Design structures and mechanical components, route cables and piping, etc. - Wayne
    • Arrange for piping designer - George
      • Design piping to vent N2.
      • Design warm and cold He supply/return systems, LN2 supply system.
    • Retrieve rails from IU - George and Elliott
    • Get three racks from Randy H or from CC - Mark S and Elliott W
    • Determine cryogen supply/return needs - George
    • Arrange for cryogen supply/return with Dana Arenius (and Kelly Dixon?)- George and Elliott


Components

  • Platform
    • Entire platform and supports will be moved when changing coils.
    • Must account for magnetic forces.
    • Ladder needs to be shortened and straightened.
    • Must include cable trays and strain relief, especially for power connections.
  • Rails
    • Currently in transportainer at IU, George will have a look when he goes out there.
  • Cryo can and heat exchanger
    • RFQ out for cryo can, no delivery date yet.
  • Piping
    • Not clear where N2 vent this will be routed.
    • Must incorporate drip pan under N2 vent due to icing.
  • Electrical power
    • Need to work out where outlets are needed.


  • Power supply
    • Integral dump resistor.
    • Need switch nearby.


  • Coils and yokes
    • Are yoke modifications are needed?


  • Controls system
    • Will wire up as per final system.
    • Should we go with separate chassis for each coil?


  • Misc tools, tables, chairs, ladders, etc.
    • What do we need? Can we beg, borrow, and/or steal?


  • To Do:
    • Understand how to deal with dump resistor in power supply - Mark S
    • Order cryo can - George
    • Verify all cryo transfer lines and U-tubes are available on site - Mark S and George
    • Verify we can borrow heat exchanger from Hall A - George
    • Get heat exchanger - Mark S
    • Order remaining piping - ?
    • Design cryo and electrical/electronics break system - George and Mark S
    • Arrange for yoke modifications if needed - George
    • Determine if sensible to use one PLC chassis per coil - Mark S and Elliott
    • Order signal conditioners and related items - Mark S and Elliott
    • Order PLC components - Elliott


Programming

  • Notes:
    • Mark W will do all programming.
    • Can borrow lots of code from Steve Lassiter and co.
    • Single computer will perform all control and monitoring tasks.
  • To Do:
    • Install new memory in controls computer - Elliott and Mark W
    • Purchase new software licenses - Elliott
    • Install all software on controls computer - Mark W
    • Borrow code from Steve Lassiter - Mark W
    • Explain overall control strategy to Mark W - George
    • Determine what needs to be archived and how often - George
    • Design and implement full control and archiving system - Mark W


Staging

  • Notes:
    • Will instrument controls racks in F117, then move to Test Lab.
    • Will instrument for final 4-coil system.
  • To Do:
    • Rearrange F117 - Mark S and Beni
    • Get and move 3 racks into F117 - Mark S
    • Verify adequate staging areas available in Test Lab - George, Wayne and Mark S


Reviews

  • Notes:
    • Micro-review of PLC vendor choice completed, waiting for report.
    • Need cryo, electrical, mechanical, and operations reviews.


  • To Do:
    • Write thank-you letter to Jonathan Creel and Omar Garza for participating in PLC vendor review - Elliott
    • Write appropriate documentation - George, Mark S, Wayne and Elliott
    • Set up all reviews - George and Elliott


Construction

  • Notes:
    • Do we have enough manpower?


  • To Do:
    • Arrange for any coil or yoke modifications - George
    • Order controls equipment - Mark S and Elliott
    • Arrange for telephone and networking in test area - Elliott
    • Arrange for installation of electrical infrastructure - Mark S
    • Move controls racks to Test Lab - Mark S
    • Move computer to Test Lab - Mark W and Elliott
    • Install all components - Mark S
    • Hook up controls system - Mark S, Mark W and Elliott
    • Verify operation of control/archiving system - Mark W, Mark S, George and Elliott


Coil Tests

  • Notes:
    • Purpose:
      • Verify correct operation of all coils.
      • Measure coil strains up to full current (1600 A).
    • Will take about one month per coil.
    • Will take a few days to cool down a single coil (warm up?).


  • To Do:
    • Create test plan - George