== Dry Run Schedule for the Review ==
 
== Dry Run Schedule for the Review ==
=== First round of dry runs (week of October 27) ===
+
=== First round of dry runs (week of November 3rd) ===
 
* Thursday Nov 6 and Friday Nov 7
 
* Thursday Nov 6 and Friday Nov 7
  

Revision as of 08:11, 9 October 2008

The Hall D/GlueX Tagger and Beamline Review

Material Prepared for the Review

Relevant Wiki Pages

Dry Run Schedule for the Review

First round of dry runs (week of November 3rd)

  • Thursday Nov 6 and Friday Nov 7
  1. Overview of Hall D Detector E. C. Aschenauer
  2. 12 GeV Electron Beam Y. Roblin
  3. Photon Beam Overview R. Jones
  4. Beam Simulations A. Somov
  5. Photon Beam Line T. Whitlatch
  6. Magnet Design J. Stewart
  7. Tagger Optics D. Sober
  8. Fixed Array Hodoscope F. Klein
  9. Microscope I. Senderovich
  10. Pair Spectrometer J. Stewart
  11. Diamond Selection and Testing R. Jones

Second round of dry runs (weeks of November 3 and 10)

  • Wednesday F326/327 November 5
  1. Overview of Hall D Detector E. C. Aschenauer
  2. 12 GeV Electron Beam Y. Roblin
  3. Photon Beam Overview R. Jones
  4. Beam Simulations A. Somov
  5. Photon Beam Line T. Whitlatch
  6. Magnet Design J. Stewart
  7. Tagger Optics D. Sober
  8. Fixed Array Hodoscope F. Klein
  9. Microscope I. Senderovich
  10. Pair Spectrometer J. Stewart
  11. Diamond Selection and Testing R. Jones

Main Review

  1. Review: November 19 and 20.
  2. issues that need special attention