Difference between revisions of "Tagger and Beamline Review"

From GlueXWiki
Jump to: navigation, search
(Second round of dry runs (week of November 10))
(Second round of dry runs (week of November 10))
Line 51: Line 51:
  
 
=== Second round of dry runs (week of November 10) ===
 
=== Second round of dry runs (week of November 10) ===
* Thuesday Nov 11 thru Friday Nov 14
+
* Tuesday Nov 11 thru Friday Nov 14
  
#Nov 11 1:00 - 2:30 (F326/327) 12 GeV Electron Beam Y. Roblin
+
*Tuesday, November 11, 2008 Room F326/327
 +
1:00 - 2:30 12 GeV Electron Beam         Y. Roblin
  
#Nov 12 9:00-10:30 (F326/327) Beam Simulations A. Somov
+
*Wednesday, November 12, 2008 Room F326/327
#Nov 12 3:30-5:00 (F326/327)Photon Beam Overview R. Jones
+
9:00-10:30 Beam Simulations                 A. Somov
 +
3:30-5:00 Photon Beam Overview                 R. Jones
  
#Nov 13 8:00-9:00 (F326/327)Microscope I. Senderovich
+
*Thursday, November 13, 2008 Room F326/327
#Nov 13 9:00-10:00 (F326/327)Tagger Optics D. Sober
+
8:00-9:00   Microscope                         I. Senderovich
#Nov 13 10:00-11:30 (F326/327)Magnet Design J. Stewart
+
9:00-10:00 Tagger Optics                 D. Sober
#Nov 13 3:00-4:30 (F326/327)Diamond Selection and Testing R. Jones
+
10:00-11:30 Magnet Design                 J. Stewart
 +
3:00-4:30   Diamond Selection and Testing R. Jones
  
#Nov 14 8:00-9:00 (F326/327) Overview of Hall D Detector E. C. Aschenauer  
+
*Friday, November 14, 2008 Room F326/327
#Nov 14 9:00-10:30 (F326/327)Photon Beam Line T. Whitlatch  
+
8:00-9:00   Overview of Hall D Detector         E. C. Aschenauer  
#Nov 14 10:30-12:00 (F326/327)Fixed Array Hodoscope F. Klein
+
9:00-10:30 Photon Beam Line                 T. Whitlatch  
#Nov 14 2:30-4:00 (F326/327)Pair Spectrometer J. Stewart
+
10:30-12:00 Fixed Array Hodoscope         F. Klein
 +
2:30-4:00   Pair Spectrometer         J. Stewart
  
 
=== Main Review ===
 
=== Main Review ===
 
# Review: November 19 and 20.
 
# Review: November 19 and 20.
 
# issues that need special attention
 
# issues that need special attention

Revision as of 10:12, 22 October 2008

The Hall D/GlueX Tagger and Beamline Review

Material Prepared for the Review

  • Pre-brief Material for the reviewers
  1. General Documents
  2. Tagging Spectrometer
  3. Electron Machine
  4. Pair Spectrometer

Relevant Wiki Pages

Dry Run Schedule for the Review

First round of dry runs (week of November 3rd)

  • Thursday Nov 6 Friday Nov 7 and monday Nov 10


  • Nov 6 9:00 - 10:30 (F326/327) R. Jones Photon Beam Overview
  • Nov 6 10:30 - 12:00 (F326/327) A. Somov Beam Simulations
  • Nov 6 2:15 - 3:30 (F326/327) J. Stewart Pair Spectrometer
  • Nov 6 3:30- 4:30 (F326/327) I. Senderovich Microscope
  • Nov 6 4:30 - 5:30 (F326/327) D. Sober Tagger Optics
  • -
  • Nov 7 9:00 - 10:30 (L207) R. Jones Diamond Selection and Testing
  • Nov 7 10:30-12:00 (L207) T. Whitlatch Photon Beam Line
  • Nov 7 2:15 - 4:00 (F326/327) F. Klein Fixed Array Hodoscope
  • -
  • Nov 10 9:00 - 10:30 (F326/327) J. Stewart Magnet Design
  • Nov 10 1:00 - 2:30 (F326/327) Y. Roblin 12 GeV Electron Beam

Richard not available 12:00 - 14:00

Second round of dry runs (week of November 10)

  • Tuesday Nov 11 thru Friday Nov 14
  • Tuesday, November 11, 2008 Room F326/327

1:00 - 2:30 12 GeV Electron Beam Y. Roblin

  • Wednesday, November 12, 2008 Room F326/327
9:00-10:30 Beam Simulations	                A. Somov
3:30-5:00 Photon Beam Overview	                R. Jones
  • Thursday, November 13, 2008 Room F326/327

8:00-9:00 Microscope I. Senderovich 9:00-10:00 Tagger Optics D. Sober 10:00-11:30 Magnet Design J. Stewart 3:00-4:30 Diamond Selection and Testing R. Jones

  • Friday, November 14, 2008 Room F326/327

8:00-9:00 Overview of Hall D Detector E. C. Aschenauer 9:00-10:30 Photon Beam Line T. Whitlatch 10:30-12:00 Fixed Array Hodoscope F. Klein 2:30-4:00 Pair Spectrometer J. Stewart

Main Review

  1. Review: November 19 and 20.
  2. issues that need special attention