# '''ESNET''': join DOE ECS videoconferencing room 8542553.
 
# '''ESNET''': join DOE ECS videoconferencing room 8542553.
 
# '''EVO''': in community Gluex, look for "Photon Beam Review Dry Runs" meeting.
 
# '''EVO''': in community Gluex, look for "Photon Beam Review Dry Runs" meeting.
# '''Telephone''': connect using the evo telephone bridge (for numbers see [[Tagged Beam Group Biweekly Meetings|listings at the bottom of this page]]), with meeting Id's listed in parentheses below, and pass code 6626.
+
# '''Telephone''': connect using the evo telephone bridge (for numbers, [[Tagged Beam Group Biweekly Meetings|click here]]), with meeting Id's listed in parentheses below, and pass code 6626.
  
 
== First round of dry runs (week of November 3rd) ==
 
== First round of dry runs (week of November 3rd) ==

Revision as of 18:58, 5 November 2008

The Hall D/GlueX Tagger and Beamline Review

Material Prepared for the Review

  • Pre-brief Material for the reviewers
  1. General Documents
  2. Tagging Spectrometer
  3. Electron Machine
  4. Fixed Hodoscope
  5. The microscope detector
  6. Pair Spectrometer
  7. Plan for what we want to study with diamonds.
  8. Simulations of collimatior cave and pair spectrometer background- Alex
  9. Trigger rates and background - Alex

Relevant Wiki Pages

Dry Run Schedule for the Review

Connection Instructions:

  1. ESNET: join DOE ECS videoconferencing room 8542553.
  2. EVO: in community Gluex, look for "Photon Beam Review Dry Runs" meeting.
  3. Telephone: connect using the evo telephone bridge (for numbers, click here), with meeting Id's listed in parentheses below, and pass code 6626.

First round of dry runs (week of November 3rd)

Thursday, November 6, 2008 Room F326/327

  • 9:00-10:30--- Photon Beam Overview--- R. Jones
  • 10:30-12:00--- Beam Simulations--- A. Somov
  • 2:15-3:30--- Pair Spectrometer --- J. Stewart
  • 3:30-4:30--- Microscope--- I. Senderovich
  • 4:30-5:30--- Tagger Optics--- D. Sober

Friday, November 7, 2008 Room F326/327 and L207

  • 9:00-10:30 (L207) Diamond Selection and Testing--- R. Jones
  • 10:30-12:00 (L207) Photon Beam Line--- T. Whitlatch
  • 2:15-4:00 (F326/327) Fixed Array Hodoscope--- F. Klein

Monday, November 10, 2008 Room F326/327

  • 9:00-10:30--- Magnet Design--- J. Stewart
  • 1:00-2:30--- 12 GeV Electron Beam--- Y. Roblin

Richard not available 12:00 - 14:00

Second round of dry runs (week of November 10)

Tuesday, November 11, 2008 Room F326/327

  • 1:00-2:30--- Beam Simulations--- A. Somov

Wednesday, November 12, 2008 Room F326/327

  • 9:00-10:30--- 12 GeV Electron Beam--- Y. Roblin
  • 3:30-5:00--- Photon Beam Overview--- R. Jones

Thursday, November 13, 2008 Room F326/327

  • 8:00-9:00--- Microscope--- I. Senderovich
  • 9:00-10:00--- Tagger Optics--- D. Sober
  • 10:00-11:30--- Magnet Design--- J. Stewart
  • 3:00-4:30--- Diamond Selection and Testing--- R. Jones

Friday, November 14, 2008 Room F326/327

  • 8:00-9:00--- Overview of Hall D Detector--- E. C. Aschenauer
  • 9:00-10:30--- Photon Beam Line--- T. Whitlatch
  • 10:30-12:00--- Fixed Array Hodoscope--- F. Klein
  • 2:30-4:00--- Pair Spectrometer--- J. Stewart

Main Review

  1. Review: November 19 and 20.
  2. issues that need special attention