Test Setup for SiPMs
From GlueXWiki
Contents
Test of First Article of Hamamatsu SiPMs
Time Line
- Mid Feb.2012: 10-20pcs partial shipment of first article units
- Mid Mar.2012: Delivery remainder first article units (60-70pcs)
- End Apr.2012: First article approval
- End Jul.2012: 1st delivery 500pcs
- End Aug.2012: 2nd delivery 500pcs
- End Sept.2012: 3rd delivery 120pcs