Test of First Article of Hamamatsu SiPMs

Time Line

  1. Mid Feb.2012: 10-20pcs partial shipment of first article units
  2. Mid Mar.2012: Delivery remainder first article units (60-70pcs)
  3. End Apr.2012: First article approval
  4. End Jul.2012: 1st delivery 500pcs
  5. End Aug.2012: 2nd delivery 500pcs
  6. End Sept.2012: 3rd delivery 120pcs