Difference between revisions of "Fall 2014 Commissioning Plan"
From Hall D Ops Wiki
Line 1: | Line 1: | ||
__TOC__ | __TOC__ | ||
+ | =General Information= | ||
* Expected Staffing: | * Expected Staffing: | ||
** Run Coordinator: To be named | ** Run Coordinator: To be named | ||
Line 7: | Line 8: | ||
** MCC meeting at 7:00am | ** MCC meeting at 7:00am | ||
** Daily run meeting broadcast on bluejeans 10:30am?? | ** Daily run meeting broadcast on bluejeans 10:30am?? | ||
+ | * Activity Priority | ||
+ | ** High: Activity should be completed, contingencies in place for issues. | ||
+ | ** Medium: Desirable to complete the activity. | ||
+ | ** Low: Activity would be useful if time permits us to do it. | ||
+ | * Deferred Activity | ||
+ | ** Installation of liquid hydrogen target. | ||
+ | ** Installation of diamond radiator in goniometer. | ||
+ | ** Running data at 1350A solenoid current. | ||
+ | =Run Plan= | ||
==[[Tune Electron Beam]]== | ==[[Tune Electron Beam]]== | ||
==[[Tune Photon Beam]]== | ==[[Tune Photon Beam]]== |
Revision as of 12:09, 2 July 2014
Contents
General Information
- Expected Staffing:
- Run Coordinator: To be named
- Online Shifts: 3 persons per shift, one with solenoid training.
- Offline Shifts: at least two people looking at data written to tape.
- Coordination Activities:
- MCC meeting at 7:00am
- Daily run meeting broadcast on bluejeans 10:30am??
- Activity Priority
- High: Activity should be completed, contingencies in place for issues.
- Medium: Desirable to complete the activity.
- Low: Activity would be useful if time permits us to do it.
- Deferred Activity
- Installation of liquid hydrogen target.
- Installation of diamond radiator in goniometer.
- Running data at 1350A solenoid current.