Difference between revisions of "Fall 2014 Commissioning Plan"
From Hall D Ops Wiki
(→Tune Electron Beam#Tune Electron Beam) |
|||
Line 17: | Line 17: | ||
** Running data at 1350A solenoid current. | ** Running data at 1350A solenoid current. | ||
=Run Plan= | =Run Plan= | ||
− | ==[[ | + | ==[[Tune Electron Beam]]== |
− | ==[[ | + | ==[[Tune Photon Beam]]== |
− | ==[[ | + | ==[[One Week Pause in Running]]== |
− | ==[[ | + | ==[[Collect Beam Data for Detector Checkout]]== |
− | ==[[ | + | ==[[Optimize Detector Settings]]== |
− | ==[[ | + | ==[[Drift Chamber Alignment]]== |
− | ==[[ | + | ==[[Collect More Regular Data]]== |
Revision as of 12:59, 2 July 2014
Contents
General Information
- Expected Staffing:
- Run Coordinator: To be named
- Online Shifts: 3 persons per shift, one with solenoid training.
- Offline Shifts: at least two people looking at data written to tape.
- Coordination Activities:
- MCC meeting at 7:00am
- Daily run meeting broadcast on bluejeans 10:30am??
- Activity Priority
- High: Activity should be completed, contingencies in place for issues.
- Medium: Desirable to complete the activity.
- Low: Activity would be useful if time permits us to do it.
- Deferred Activity
- Installation of liquid hydrogen target.
- Installation of diamond radiator in goniometer.
- Running data at 1350A solenoid current.