Fall 2014 Commissioning Plan
From Hall D Ops Wiki
Revision as of 12:58, 2 July 2014 by Cmeyer (Talk | contribs) (→Tune Electron Beam#Tune Electron Beam)
Contents
- 1 General Information
- 2 Run Plan
- 2.1 Tune Electron Beam#Tune Electron Beam Tune Electron Beam
- 2.2 Tune Photon Beam#Tune Photon Beam
- 2.3 One Week Pause in Running#One Week Pause in Running
- 2.4 Collect Beam Data for Detector Checkout#Collect Beam Data for Detector Checkout
- 2.5 Optimize Detector Settings#Optimize Detector Settings
- 2.6 Drift Chamber Alignment#Drift Chamber Alignment
- 2.7 Collect More Regular Data#Collect More Regular Data
General Information
- Expected Staffing:
- Run Coordinator: To be named
- Online Shifts: 3 persons per shift, one with solenoid training.
- Offline Shifts: at least two people looking at data written to tape.
- Coordination Activities:
- MCC meeting at 7:00am
- Daily run meeting broadcast on bluejeans 10:30am??
- Activity Priority
- High: Activity should be completed, contingencies in place for issues.
- Medium: Desirable to complete the activity.
- Low: Activity would be useful if time permits us to do it.
- Deferred Activity
- Installation of liquid hydrogen target.
- Installation of diamond radiator in goniometer.
- Running data at 1350A solenoid current.