One Week Pause in Running
- Goal: Reinstall tagger detectors/electronics and check data.
- Schedule: Start Oct 14, duration 5-7 days depends on the accelerator program to be carried out meanwhile
- Responsibility: Hall D
- Priority: High
- Conditions:
- Beam off in the Hall.
- Acivities
- Reinstall the tagger detector, TAGM and the electronics, reconnect the cables.
- Check validity of the data taken so far. Use as feedback to detector settings.
- Check/modify the online monitoring histograms based on data.
- Using reconstructed tracks find the location of the beam spot