'''This page gives the run plan for the Fall 2014 commissioning. It is a controlled document that can be edited only by E. Chudakov, E. Smith or A. Deur. Suggestions and comments should be send to them.
==Tune Electron Beam==
+
'''
# Goal: Get electron beam to the dump in the tagger hall.
+
 
# Responsibility: Accelerator, HallD, RadCon.
+
<span style="color:#ff00ff">Items in pink indicate missing information. </span>
# Conditions:
+
 
#* Tagger hall equipment removed or shielded. This includes the microscope (TAGM) and the electronics.
+
=General Information=
#* Pulsed beam may be used.
+
 
#* No radiator installed.
+
This document describes the run plan and procedures for the Hall D Fall 2014 commissioning.  
#* Collimator blocks the photon beamline to Hall D.
+
 
# Activities:
+
* Goals for the Fall 2014 run (expected durations are given in parenthesis)
#* Tune beam to the dump, check the beam specification.
+
*# See start dates in the run coordination meeting pages [https://halldweb1.jlab.org/wiki/index.php/Run_Coordination_Meetings#Meeting_General_Agenda here]
#* Check radiation levels in the tagger hall.
+
*# Clean tune of the electron beam into the Tagger Dump (13 days)
#* Check for photons and radiation levels in the collimator cave.
+
*# Commissioning of the unpolarized photon beam (4 days)
==Tune Photon Beam==
+
*# Reinstall Tagger electronics (6 days)
# Goal: Tune the photon beam to go through the collimator, the experimental target area, and into the photon beam dump.
+
*# Commissioning of the Hall D equipment under "soft" conditions (17 days):  
# Responsibility: HallD, Accelerator, RadCon.
+
*#* Low-intensity unpolarized photon beam <10 MHz/GeV at the endpoint
# Conditions:
+
*#* Thin solid targets instead of the regular liquid hydrogen target
#* Tagger hall equipment removed or shielded. This includes the microscope (TAGM) and the electronics.
+
*#* Solenoid current 1200 A instead of the nominal 1300 A
#* Beam 50nA CW (if possible).
+
* Schedule and Hall Availability: The tentative plan is:
#* Radiator 10<sup>-4</sup> RL.
+
*# Accelerator: beam recovery and 5.5 pass beam tune to the dumplette Oct 08-17. Hall D/Tagger are open.
#* Collimator hole is 3.5mm at nominal beam position.
+
*# Accelerator: electron beam tune to the Tagger Dump, 17-oct-14 - 21-Oct-14. Hall D/Tagger are locked. TAGM and the electronics are removed from the Tagger Hall.
#* Solenoid on with current ~1000A.
+
*# Accelerator/Hall D: Photon beam tune to Hall D and the initial equipment checkout, Oct 22-26. Halls are locked.  
#* GlueX detectors off (except peripheral such as BCAL)
+
*# Hall D: Re-installation of the Tagger equipment (TAGM and the electronics), Oct 27- Nov 02. Halls are open.
#* No target in place (use air along beamline as target).
+
*# Hall D: Equipment commissioning with photon beam, Nov 03-18. Halls are locked.
# Activities
+
* Expected Staffing and responsibilities:
#* Use the beam profiler to move the photon beam to the hole in the collimator. (Accel, Hall D)
+
**The Run Coordinator (RC, Alexandre Deur) oversees the commissioning.  
#* Check radiation levels in the collimator cave and HallD. (RadCon)
+
**<span style="color:black">The Physics Division Liaison (PDL, Yi Qiang) </span> and Hall D Work Coordinator/Safety Warden (T. Carstens) verify that the proper safety rules are followed.  
#* Turn the PS magnet on and install a 10<sup>-3</sup> converter. Tune the PS coarse detectors (Hall D).
+
**The Analysis Coordinator (Paul Mattione)  will organize the off-line analysis effort.  
#* Use the PS coarse detectors to verify the beam location.
+
**Individuals responsible for each commissioning step are named in the section describing the step. They are also responsible for logging in the ELog the summary of how the step proceeded and other relevant information.  
#* Insert a convertor in the PS and leave running with its own trigger throughout the run period.
+
**Shifts
#* Calibrate the active collimator by scanning (desirable activity). (HallD and Accelerator)
+
*** Online Shifts (Nominally 2 persons per shift, one with solenoid training.)
#* Use other detectors (under discussion) to verify the beam position with respect to the beam pipes and the target (if time permits) (Hall D)
+
**** Electron beam commissioning: Shifts will be scheduled but be stand-by shifts by default. The counting room will be manned only if accelerator needs a contact, or if Hall D expertise is needed to support the beam tuning (e.g. to operate the amorphous collimator harp). If so, the shift leader will be asked to be present. If the task demands it, the two-man rule must be obeyed.  
#* Turn detectors on slowly, moving in from the peripheral to the center. Monitor the rates and background levels. (Hall D)
+
**** Photon beam commissioning: Only beam line equipment and the solenoid will be operated. The detectors will be turned off for most of the time, with the possible exception of BCAL and the outer rings of FCAL. The counting room will be manned by two shift persons, one with solenoid training, and the experts necessary to the conduct of specific parts of the run plan. The RC will assign the experts. The third shift taker will be on stand-by.
#* Insert a thin target at the nominal target position. Set the regular trigger and take data for about 1 shift.
+
**** Initial detector testing with the tagger equipment still removed: Once the photon beam is commissioned the Hall D detectors will be turned on, Online shifts will be operated by three persons, one with solenoid training.  
==One Week Pause in Running==
+
**** Re-installation of the tagger equipment: Shifts are on stand-by.
# Goal: Reinstall tagger detectors and check data.
+
**** Detector commissioning : Online shifts will be operated by three persons, one with solenoid training.  
# Responsibility: HallD
+
*** Offline Shifts: None.
# Conditions:
+
* Coordination Activities:
#* Beam off in the Hall.
+
** The RC will attend the MCC meetings at 7:50am and 8:00am and the weekly MCC meeting (Wednesday, 1:30pm). The PDL will attend the weekly MCC meeting.
# Acivities
+
** Daily run meetings broadcasted on Bluejeans will occur at 10:30am in the counting house conference room. The Analysis Coordinator will be responsible for organizing and chairing the meeting.  
#* Reinstall the tagger detectors, TAGM and TAGH.
+
** Links to accelerator schedules:
#* Check validity of data offline. Use as feedback to detector settings.
+
***[http://opsweb.acc.jlab.org/TJ3/12GeV_CEBAF/Fall2014.html CEBAF 12 GeV Commissioning calendar]
#* Check/modify the online monitoring histograms based on data.
+
***[https://accweb.acc.jlab.org/calendar/  Scheduled Accelerator Down (SAD)/Maintenance Calendar]
==Collect Beam Data for Detector Checkout==
+
***[http://accboard.acc.jlab.org/ http://accboard.acc.jlab.org/]
# Goal: Collect 5 days of beam data.
+
** Links to beam parameters/radiation level monitoring:
# Responsibility: HallD
+
***[https://www.jlab.org/accel/RadCon/opsgraphs/8h/halld_8h.pdf Last 8-hours plots showing 1-minute, 10-minute, and hourly averages]
# Conditions:
+
***[https://www.jlab.org/accel/RadCon/opsgraphs/24h/halld_24h.pdf Same but Last 24-hours]
#* Tagger hall equipment in place and operating.
+
***[https://www.jlab.org/accel/RadCon/opsgraphs/72h/halld_72h.pdf Same but Last 72-hours]
#* Beam 50nA CW
+
***Week, month, and quarter (3 months) plots also exist, with similar web addresses.
#* Radiator is 10<sup>-4</sup>.
+
*** A map of the radiation monitors [[File:rad_det_map.jpg | 100px]]
#* Collimator hole is 3.5mm.
+
* Activity Priority
#* Solenoid on at 1200A
+
** High: Activity should be completed, contingencies in place for issues.
#* GlueX detectors are on.
+
** Medium: Desirable to complete the activity.
#* Thin commissioning target at nominal position.
+
** Low: Activity would be useful if time permits us to do it.
# Activities
+
* Activities planned for the next run in Spring 2015:
#* Verify photon beam position and background levels.
+
** Installation and operations of the liquid hydrogen target.
#* Take data with the regular trigger for five days
+
** Installation and operation of diamond radiators in goniometer.
==Optimize Detector Settings==
+
** Running at 1300A solenoid current.
# Goal: Verify optimal settings for detectors.
+
 
# Responsibility: HallD
+
= Beam Configuration Parameters =
# Conditions:
+
*  Energy of Beam: expected ~ 10.1 GeV
#* Tagger hall equipment in place and operating.  
+
* Beam current:
#* Beam 50nA CW
+
** Electron beam tuning is done with pulsed beam 4-10 &micro;A, duty cycle 1.5%, average current 60-150nA (see the tune beam description [https://halldweb1.jlab.org/wiki/index.php/Tune_mode here])
#* Radiator is 10<sup>-4</sup>.
+
** Photon beam operations: CW 50-200 nA
#* Collimator hole is 3.5mm.
+
* Radiators:
#* Solenoid on at 1200A
+
** 1.64 &micro;m Al (1.86&middot;10<sup>-5</sup> R.L., see [https://logbooks.jlab.org/entry/3631428 study])
#* GlueX detectors are on.
+
** 10 &micro;m Al (11.2&middot;10<sup>-5</sup> R.L.)
#* Thin commissioning target at nominal position.
+
** 30 &micro;m Al (33.7&middot;10<sup>-5</sup> R.L.)
# Activities
+
* Collimator hole: 5 mm diameter
#* If time permits, dedicated running to optimize settings of detectors will be carried out.
+
* The commissioning targets are disks of 3.19 cm diameter. Only one disk can be installed at a time. The z-position of a disk can be moved 12 cm downstream to 32 cm upstream relative to the nominal Hall D cryotarget center (60 cm downstream of the downstream end of the upstream solenoid end-cap). The available disks are:
==Drift Chamber Alignment==
+
**  10mm thick disk of CH<sub>2</sub> (HDPE, high density polyethylene, density 0.93-0.97 g/cm<sup>3</sup> ), 0.95 g/cm<sup>2</sup>, ~1.2% R.L.
# Goal: Collect data with no or low field.
+
** 2mm thick disk CH<sub>2</sub> (HDPE)
# Responsibility: HallD
+
** 2mm thick inside a 20mm diameter area and 7mm thick outside (HDPE)
# Conditions:
+
** 3.4mm thick graphite disk, 0.75 g/cm<sup>2</sup>, 1.8% R.L.
#* Tagger hall equipment in place and operating.
+
** Al. cross made of 1.59 mm diameter wires
#* Beam 50nA CW
+
** 1cm long Al. cylinder with an equilateral triangle hole inside. The triangle edge lengths are 2.5 cm
#* Radiator is 10<sup>-4</sup>.
+
 
#* Collimator hole is 3.5mm.
+
=Run Plan=
#* Solenoid 0-300A depending on backgrounds.
+
 
#* GlueX detectors are on.
+
'''Commissioning time chart''':      [[File:schedule.jpg|700px|thumb|left| Commissioning time chart. Time t=0 corresponds to the Hall being locked-up for beam tunning. With the present schedule, it is sometime in the first half of Oct. The horizontal scale is the time during which beam is available (in other word, it would be the real time with 100% of beam efficiency). The task time estimates given on the plot have 100% contingency.  ]]
#* Thin commissioning target at various positions.
+
 
# Activities
+
==[[Tune Electron Beam]]==
#* If time permits, collect data with target in several positions.
+
 
 +
==[[Tune Photon Beam and collect data for initial detector checkout]]==
 +
==[[One Week Pause in Running]]==
 +
==[[Finalize Photon Beam Commissioning and Optimize Detector Settings]]==
 +
 
 +
==[[Drift Chamber Alignment]]==
 +
==[[Collect More Regular Data]]==
 +
==[[Post-thanksgiving period]]==

Latest revision as of 16:28, 26 November 2018

This page gives the run plan for the Fall 2014 commissioning. It is a controlled document that can be edited only by E. Chudakov, E. Smith or A. Deur. Suggestions and comments should be send to them.

Items in pink indicate missing information.

General Information

This document describes the run plan and procedures for the Hall D Fall 2014 commissioning.

  • Goals for the Fall 2014 run (expected durations are given in parenthesis)
    1. See start dates in the run coordination meeting pages here
    2. Clean tune of the electron beam into the Tagger Dump (13 days)
    3. Commissioning of the unpolarized photon beam (4 days)
    4. Reinstall Tagger electronics (6 days)
    5. Commissioning of the Hall D equipment under "soft" conditions (17 days):
      • Low-intensity unpolarized photon beam <10 MHz/GeV at the endpoint
      • Thin solid targets instead of the regular liquid hydrogen target
      • Solenoid current 1200 A instead of the nominal 1300 A
  • Schedule and Hall Availability: The tentative plan is:
    1. Accelerator: beam recovery and 5.5 pass beam tune to the dumplette Oct 08-17. Hall D/Tagger are open.
    2. Accelerator: electron beam tune to the Tagger Dump, 17-oct-14 - 21-Oct-14. Hall D/Tagger are locked. TAGM and the electronics are removed from the Tagger Hall.
    3. Accelerator/Hall D: Photon beam tune to Hall D and the initial equipment checkout, Oct 22-26. Halls are locked.
    4. Hall D: Re-installation of the Tagger equipment (TAGM and the electronics), Oct 27- Nov 02. Halls are open.
    5. Hall D: Equipment commissioning with photon beam, Nov 03-18. Halls are locked.
  • Expected Staffing and responsibilities:
    • The Run Coordinator (RC, Alexandre Deur) oversees the commissioning.
    • The Physics Division Liaison (PDL, Yi Qiang) and Hall D Work Coordinator/Safety Warden (T. Carstens) verify that the proper safety rules are followed.
    • The Analysis Coordinator (Paul Mattione) will organize the off-line analysis effort.
    • Individuals responsible for each commissioning step are named in the section describing the step. They are also responsible for logging in the ELog the summary of how the step proceeded and other relevant information.
    • Shifts
      • Online Shifts (Nominally 2 persons per shift, one with solenoid training.):
        • Electron beam commissioning: Shifts will be scheduled but be stand-by shifts by default. The counting room will be manned only if accelerator needs a contact, or if Hall D expertise is needed to support the beam tuning (e.g. to operate the amorphous collimator harp). If so, the shift leader will be asked to be present. If the task demands it, the two-man rule must be obeyed.
        • Photon beam commissioning: Only beam line equipment and the solenoid will be operated. The detectors will be turned off for most of the time, with the possible exception of BCAL and the outer rings of FCAL. The counting room will be manned by two shift persons, one with solenoid training, and the experts necessary to the conduct of specific parts of the run plan. The RC will assign the experts. The third shift taker will be on stand-by.
        • Initial detector testing with the tagger equipment still removed: Once the photon beam is commissioned the Hall D detectors will be turned on, Online shifts will be operated by three persons, one with solenoid training.
        • Re-installation of the tagger equipment: Shifts are on stand-by.
        • Detector commissioning : Online shifts will be operated by three persons, one with solenoid training.
      • Offline Shifts: None.
  • Coordination Activities:
  • Activity Priority
    • High: Activity should be completed, contingencies in place for issues.
    • Medium: Desirable to complete the activity.
    • Low: Activity would be useful if time permits us to do it.
  • Activities planned for the next run in Spring 2015:
    • Installation and operations of the liquid hydrogen target.
    • Installation and operation of diamond radiators in goniometer.
    • Running at 1300A solenoid current.

Beam Configuration Parameters

  • Energy of Beam: expected ~ 10.1 GeV
  • Beam current:
    • Electron beam tuning is done with pulsed beam 4-10 µA, duty cycle 1.5%, average current 60-150nA (see the tune beam description here)
    • Photon beam operations: CW 50-200 nA
  • Radiators:
    • 1.64 µm Al (1.86·10-5 R.L., see study)
    • 10 µm Al (11.2·10-5 R.L.)
    • 30 µm Al (33.7·10-5 R.L.)
  • Collimator hole: 5 mm diameter
  • The commissioning targets are disks of 3.19 cm diameter. Only one disk can be installed at a time. The z-position of a disk can be moved 12 cm downstream to 32 cm upstream relative to the nominal Hall D cryotarget center (60 cm downstream of the downstream end of the upstream solenoid end-cap). The available disks are:
    • 10mm thick disk of CH2 (HDPE, high density polyethylene, density 0.93-0.97 g/cm3 ), 0.95 g/cm2, ~1.2% R.L.
    • 2mm thick disk CH2 (HDPE)
    • 2mm thick inside a 20mm diameter area and 7mm thick outside (HDPE)
    • 3.4mm thick graphite disk, 0.75 g/cm2, 1.8% R.L.
    • Al. cross made of 1.59 mm diameter wires
    • 1cm long Al. cylinder with an equilateral triangle hole inside. The triangle edge lengths are 2.5 cm

Run Plan

Commissioning time chart:
Commissioning time chart. Time t=0 corresponds to the Hall being locked-up for beam tunning. With the present schedule, it is sometime in the first half of Oct. The horizontal scale is the time during which beam is available (in other word, it would be the real time with 100% of beam efficiency). The task time estimates given on the plot have 100% contingency.

Tune Electron Beam

Tune Photon Beam and collect data for initial detector checkout

One Week Pause in Running

Finalize Photon Beam Commissioning and Optimize Detector Settings

Drift Chamber Alignment

Collect More Regular Data

Post-thanksgiving period